Professional Documents
Culture Documents
04 Specs For Electrical Works - 6a and 6d
04 Specs For Electrical Works - 6a and 6d
Location
QAT
AR
Plant/Project:
Landscaping Detailed
Design
Contract
No.
2023
Pg.1 of 60
Doc No.
2023-DS-07-00002
0
RE
AAM
VV
JBS
Rev
Description
Prepared
Checked
Approved
05-Jun-2006
Date
CONTENTS
1 GENERAL
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
1.13
1.14
1.15
1.16
1.17
1.18
1.19
1.20
1.21
1.22
1.23
SITE CONDITIONS
DEFINITIONS
SCOPE OF WORKS
COMPLIANCE WITH SPECIFICATION & REGULATIONS
ELECTRICAL SUPPLY SYSTEM
PROGRAMME
CONTRACT DRAWINGS
WORKING DRAWINGS
CO-ORDINATION OF DRAWINGS
MATERIALS SUBMITTALS
MATERIALS INSPECTION
ALTERNATIVE MATERIALS
SETTING OUT OF WORKS
SAFETY
CONTRACTOR S LICENSE
PERMITS
DAMAGE TO PLANT AND MATERIALS
PROTECTIVE FINISHES
LABELS AND IDENTIFICATION
WORKS TEST AND CERTIFICATE
OPERATION AND MAINTENANCE MANUALS
AS BUILT DRAWINGS
PERIOD OF MAINTENANCE
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3 LIGHT FIXTURES
4 COMMUNICATION SYSTEM
5.1
5.2
5.3
5.4
5.5
5.6
Page 2 of 60
OVERVIEW
INSTRUCTIONS TO BIDDERS
SCOPE OF WORK
FIRE ALARM SYSTEM
ANALOGUE ADDRESSABLE FIRE ALARM CONTROL PANEL NETWORK
ANALOGUE ADDRESSABLE DEVICES
3
3
3
3
3
3
05-06-2006
EARTHING
BONDING
WIRING & INSTALLATION :
TESTING , COMMISSIONING & HANDING OVER:
3
3
3
3
3
9 SPARES
Page 3 of 60
05-06-2006
Detailed Design Issue
1 GENERAL
1.1
SITE CONDITIONS
Maximum Ambient
Temperature
Winter
1.2
Altitude
Sea Level
95 %
5
Prevailing Wind
Westerly
North
6
Storms
Irregular
Dusty
7
Annual Rainfall
January & April
50mm
and
North
Sporadic
and
between
DEFINITIONS
used
in
these
Site
carried out.
Client
Heritage
Consultant
Contractor
QGEWC
Q-TEL
Corporation
Qatar
Public
Telecommunication
QGEWC Regulations
:
Regulations issued by the Qatar
General Electricity
and
Water
Corporation regarding the installation of
Electrical equipment, Wiring & Airconditioning of
residential and commercial
Buildings (Latest Edition).
Page 4 of 60
05-06-2006
Detailed Design Issue
IEE Regulations
:
Regulations
for
Electrical
Installations issued by the Institution of
Electrical Engineers (Latest Edition).
BS
CP
Tender Drawing
is based and
Drawings
Which
is
prepared
by
the
the purpose of
the
true
record
of
the
:
To include the provisions for al the
materials and works to be carried out by
the Contractor as per these specifications
and for the satisfactory completion of the
installation.
Approved
Consultant in
Shall
mean
APPROVED
by the
writing.
Submitted
Consultant in
Shall
mean
SUBMITTED
to
the
writing.
Accepted
Consultant in
Shall
mean
ACCEPTED
by the
writing.
Provide
Commission.
Shall
Install
Furnish
Concealed
the
:
:
mean
Supply,
Install,
Test
&
partitions.
Exposed
occupants in
Shall
mean
visible
to
building
05-06-2006
Detailed Design Issue
1.3
SCOPE OF WORKS
1.4
Wiring accessories
Telephone system
outlets only).
(conduits,
&
junction
boxes
and
REGULATIONS
The Contractor shall supply all materials which shall be new and
in new condition. The Contractor shall supply all the necessary
skilled and non-skilled Labor to complete the works in accordance
with the program of works.
The installations shall comply with the following regulations:
i.
Page 6 of 60
05-06-2006
Detailed Design Issue
ii.
iii.
iv.
1.5
:
:
Alternating current
415 volts on 3 phase and 240 volts
:
:
Plus or Minus 6%
NOTE :-
All the equipments and accessories shall be rated for 240 or 415
volts, 50 Hz, AC. No alternatives will be permissible i.e., 220 / 380
volts or 115/220 volts equipments will be summarily rejected.
Throughout this specification and on the Drawings, the following
ranges of nominal voltages (r.m.s values of a.c.) are used and
defined as follows :
Extra Low Voltage
: Normally not exceeding 50 Volts between
the Conductors or to the Earth
Low Voltage
:
exceeding 250 Volts
and the Earth
Medium Voltage
:
exceeding 650 Volts,
Page 7 of 60
05-06-2006
Detailed Design Issue
1.6
PROGRAMME
1.7
Mobilization
Drawings and Material Submittals
Approvals
Equipment Deliveries
First Fix
Main & Sub-Main Distribution Equipment
Second Fix
Fixing of Light Fixtures
Testing
Commissioning & Handing Over
CONTRACT DRAWINGS
1.8
WORKING DRAWINGS
Page 8 of 60
05-06-2006
Detailed Design Issue
i.
ii.
1.9
CO-ORDINATION OF DRAWINGS
1.10
MATERIALS SUBMITTALS
05-06-2006
Detailed Design Issue
vii.
viii.
i.
ETA on Site
Status as on date of Report
Equipment Supply
All the equipments for the project shall be procured only through
the appointed local agent in Qatar, who shall be the authorized
agent and be able to supply the spare parts etc., for the items
anytime in the future. The Contractor shall mark the same clearly
on the submittals (item No. iii. above).
In case of any item/s required to be purchased abroad directly, for
valid reasons, then the Contractor shall mention the same in the
submittal and obtain approval from the consultant specifically.
ii.
iii.
Design references
Any design, for any of the systems, detailed on the Tender
drawings, which requires amendment or differs from that available
at the time of construction, due to the change in the
manufacturers range of production or availability etc., the
Contractor shall discuss the matter and obtain a readily available
alternative from the Consultant. Accordingly, the Contractor shall
make a fresh submittal based on the Consultants advice and
obtain approval to provide the revised system.
In such cases, no cost consideration will be applicable, as the
Contractor is deemed to have studied the drawings and
specifications thoroughly as well as obtained clarifications during
the tender stage, before submitting his quotation for the execution.
1.11
MATERIALS INSPECTION
The Contractor shall inform the consultant within one week upon
receipt of all the materials at the site and arrange for the
inspection of the same. Any material used at site which is not
approved earlier specifically shall stand rejected without notice.
Any item on supply differs from the one shown on the submittal
catalogue copy or the sample submitted will also be rejected at
site. In such cases, the Contractor shall make a fresh submittal for
the item and obtain approval from the Consultant. Any time delay
caused due to the above shall be on the Contractors account.
The Contractor will have to remove the rejected materials from the
site and replace with approved materials at his own expenses. In
the event the Contractor fails to do so, the client will have the
liberty to carry out such works from other agencies and debit the
ensuing amount to the Contractor.
Page 10 of 60
05-06-2006
Detailed Design Issue
Materials Storage
The Contractor shall be responsible for the safe keeping and
storage of the materials at site and provision of such covering as
may be necessary to ensure that on completion, all items are
handed over in sound condition with all protective finishes
undamaged. The material storage, handling & protection at site
shall be strictly as per Q.C.S respective sections.
1.12
ALTERNATIVE MATERIALS
Equipments and Materials used as the basis for the design are
listed in the Schedule of Manufacturers. The tenderer shall
submit alternative proposals for any of the equipment or material
for the Consultants consideration. Only in case if the specified
item/s are not available due to valid reasons. Only in such cases,
the alternatives will be considered by the Consultant, before the
tender is accepted and the Consultants decision will be final
regarding the matter.
In case the alternatives are accepted, the acceptance of the same
will be confirmed in writing by the Consultant.
During the
execution of the contract, no alternative equipment, materials or
fittings will be permitted other than the approved and the
Contractor is fore-warned that any item provided by him which is
not upto the specification, must be replaced at his own expense.
In cases where time will not permit, then such replacements shall
be at the clients convenience, but nevertheless at the Contractors
expenses etc.
1.13
1.14
SAFETY
Page 11 of 60
05-06-2006
Detailed Design Issue
1.15
CONTRACTORS LICENSE
1.16
PERMITS
1.17
05-06-2006
Detailed Design Issue
1.18
PROTECTIVE FINISHES
1.20
of
be
the
for
1.21
05-06-2006
Detailed Design Issue
a.
Step by step operating procedures.
b.
Preventive maintenance schedule.
c.
Technical literature.
d.
Spare parts list
e.
Manufacturer's name, address, telex no., Fax no. telephone
no., and
contact
person. - Local as well as overseas.
f.
Work test certificates, if any.
g.
1.22
AS BUILT DRAWINGS
1.23
PERIOD OF MAINTENANCE
Page 14 of 60
05-06-2006
Detailed Design Issue
2.1
05-06-2006
Detailed Design Issue
does not match the specified 25kA, the current limiting devices
shall be provided in accordance with Table No.1 of QGEWC
regulations. All breakers of the SUB MAIN PANELS should be of
same manufacturer as that of MV panel breakers to achieve better
discrimination.
The ratings of all MCCB's incorporated in
switchboards are shown in detail on the drawings.
the
sub-main
2.2
DISTRIBUTION BOARDS
05-06-2006
Detailed Design Issue
Page 17 of 60
05-06-2006
Detailed Design Issue
2.3
05-06-2006
Detailed Design Issue
Metering functions
2.4
05-06-2006
Detailed Design Issue
Moulded case circuit breakers (MCCB) shall comply with IEC 9472 latest edition and shall be of high quality mouldings with all
essential parts treated for corrosion resistance and plated for good
electrical conductivity.
Page 20 of 60
05-06-2006
Detailed Design Issue
2.5
Long time protection from 40% to 100% of the trip unit rating,
(MCB)
2.5
FUSES
05-06-2006
Detailed Design Issue
2.6
The Mini feeder pillar for the Museum of Islamic Arts landscaping
shall have an architect outlook, unlike the usual box-type features.
The size and features of the feeder pillar compartment shall be of
highest quality and shall blend with the landscaping design
features.
Preferably, the mini feeder pillar shall be cylindrical which looks
very similar to a bollard. The mini feeder pillars shall be
strategically located throughout the landscaped areas as shown in
the drawing.
The Mini Feeder Pillars shall be factory-built assembly, tested and
certified by a competent authorizing testing body.
Mini Feeder Pillars shall be suitable for operating on a 3-phase, 4wire and 415V supply.
Mini Feeder Pillars should be symmetrical through fault rating of
25kA for 3 seconds.
Mini Feeder Pillars shall be of robust construction. The mini feeder
pillar shall have pad mounted type with flanged plate and hinged
doors made up of stainless steel in a brushed finish.
The doors shall be lockable and have concealed hinges provided
with gaskets.
The thickness of the sheet steel shall be not less than 1.5 mm.
The mini feeder pillar shall be free standing with bolt-on root.
The finished paint RAL colour, if any, shall be to engineers
approval.
The mini feeder pillar shall be split into two sections as mentioned
in the contract drawings. The incoming breaker shall be three pole
isolator as indicated in the contract drawing. Provisions for
incoming cable entry (such as cable glands, shrouds, earth plate
terminals) shall be provided to suit the required cable size as
mentioned in the contract drawing.
The first section shall feed 16Amps, 4-pole and a 16Amps 2-pole
industrial type socket outlet, both installed inside the mini feeder
pillar. Apart from that, power supply to contactor and timer control
is fed from the first section.
The entire second section of the split busbar is fed via 63amps,
4Pole, contactor along with 100mA RCD.
Page 22 of 60
05-06-2006
Detailed Design Issue
The timer control circuit shall control the entire lighting circuit.
Underwater lighting circuits shall be fed via 30mA ELCB
The main busbar for the mini feeder pillar shall be highly
conductive,
rectangular
section,
hard
drawn
copper,
electrolytically tinned suitably marked and colour coded in
accordance to the BS Standards
The short circuit rating of the busbar shall be as stated in the
drawing. There shall be separate copper bars for neutral and
earth.
2.7
i.
General:
ii.
iii.
2.8
Page 23 of 60
05-06-2006
Detailed Design Issue
Armoured Cables
The armoured cables shall be sized to comply with the following:
Page 24 of 60
05-06-2006
Detailed Design Issue
i.
ii.
iii.
05-06-2006
Detailed Design Issue
2.9
(MICC)
Page 26 of 60
05-06-2006
Detailed Design Issue
2.10
mm
mm
mm
mm
mm
dia.
dia.
dia
dia.
dia.
:
:
:
:
:
1.8
1.9
2.5
2.5
2.5
mm
mm
mm
mm
mm
05-06-2006
Detailed Design Issue
Page 28 of 60
05-06-2006
Detailed Design Issue
Page 29 of 60
05-06-2006
Detailed Design Issue
2.11
CABLE TRUNKING
G. I. Trunking
&
CABLE TRAYS
Page 30 of 60
05-06-2006
Detailed Design Issue
Page 31 of 60
05-06-2006
Detailed Design Issue
05-06-2006
Detailed Design Issue
ii
Cable Trays
The cable trays shall be of the conventional perforated pattern
with return flanges manufactured from a minimum of 2 mm or
above Aluzink steel. Aluzink is a sheet steel known for ite inherent
strength with an alloy coating consisting of Silicon (1.6%) .
Aluminium ( 55% ) for protection against corrosion and zinc
(43.4%) safeguarding the steel. The Aluzink used should be of
grade B500A, AZ150 in conformity with grade DX 51D +AZ 150 as
per EN 10215.
Sections of tray shall be jointed together with
mushroom head screws, nuts and spring washers. These shall be
plated or treated with rust inhibitor. The screws and nuts shall be
so arranged to ensure that no projecting screw threads occur on
the part of the tray upon which the cables are laid.
The cable trays shall be securely fixed to purpose made brackets
with space behind to allow the insertion of tools for the tightening
up of nuts. The brackets shall be spaced in such a way so as to
prevent sagging. The Contractor shall ensure that overall tray
arrangement is rigid. The Contractor shall include for all cable
trays necessary to be fixed at the terrace or in the false ceiling.
The cable trays shall be of sufficient width to take all cables
without crowding and shall allow for possible future additions to
the proportions of the present requirements. Cables shall be run
single; stacking will not be permitted.
Cable trays fixed to walls or flat ceilings shall be installed with the
flange outwards or downwards respectively to suit and shall be
fixed with an approved fixing with spacing and washers such that
the tray is at least 25 mm. from the surface of the wall or ceiling.
Earth continuity shall be maintained between each section of cable
tray and each total run of tray shall be effectively bonded to the
nearest earth continuity conductor.
Each length of tray shall be securely bolted to an adjacent length
with sufficient overlap to prevent sagging and twisting. Normal
bend of not less than 450 mm. shall be used.
The method of fixing each run of cable tray shall be approved by
the Consultant prior to installation. In all instances, the cable
trays shall be supported from the structure of the building. The
method of fixing the cable tray and brackets shall be approved by
the Consultant before installation.
Manufacturer should confirm a guarantee of at least 12 years for
the cable trays against any corrosion in Qatar climatic conditions.
Wherever the tee or flat bends are required to be used, they shall
be factory made. No cutting of tray shall be permitted. Wherever
necessary, the same shall be properly painted with the prior
permission of the Consultant. Deviation from the straight shall, if
possible, be made with purpose made bends. Where purpose made
bends cannot be used, the tray may be cut and the bends
fabricated on site.
Page 33 of 60
05-06-2006
Detailed Design Issue
2.12
ELECTRICAL DUCTS
2.13
WIRING ACCESSORIES
Tenderers shall note that the finishes of all the wiring accessories
shall be matching to the interior finishes metal clad matt
hairline finish
The whole product range shall be provided as a modular system
which allows different colour combinations depending on personal
taste and possibility of changing covers at later stage. The contacts
should be made of silver alloy to ensure long life of the switches.
Cover plates, frames & rockers shall allow dismounting for
redecoration/cleaning without necessity of the de- installation of
the whole insert to make touch of loaded wires impossible.
i.
Switches
The switches shall be single pole type of 240 V grade, 10 A X
rated. No derating of the switches should required in case of use
for Fluorescent or inductive loads.
These shall be of robust
construction to provide long life of operation. All the cover plates,
single pole switches, grid mounted systems and boxes shall
conform to BS 3676 and BSEN 60669 1 and shall operate on
downward mode only. Wherever more than one switch is shown
on the drawings, they shall be multi-gang and where they are
wired with different phases, phase barriers shall be used with the
warning label. Indicator lamps of the switches shall be changeable
Page 34 of 60
05-06-2006
Detailed Design Issue
iii.
Flex Outlets
The flex outlets shall be installed near the equipment like air
conditioners, water heaters and exhaust fans. These exhaust fan
outlets shall be of suitable rating having three-way terminal blocks
and brass screws for direct connection of flexible heat resistant
cables. They shall be of robust construction, of approved finish
and of very high quality. All flex outlets other than the ones for
exhaust fans shall conform to BS 5733.
iv.
Ceiling Rose
Ceiling roses shall be of approved manufacture and be of ivory
finish conforming to BS 67. All ceiling roses shall be fitted with
integral enclosure and earthing plate or connection to comply with
QGEWC regulations and shall be fitted with a break joint ring
where used on recessed conduit boxes.
v.
vi.
Page 35 of 60
05-06-2006
Detailed Design Issue
failure upto 12 hours will not change the operating time of the
time switch.
The contactor shall be of rating indicated on the drawings and
shall be 240 volts 50 Hz, 1 phase A.C. coil. It shall conform to
relevant British Standard.
The contactor shall also provide an override switch to switch on
and switch off the lights in the event time fails to operate.
Page 36 of 60
05-06-2006
Detailed Design Issue
LIGHT FIXTURES
Page 37 of 60
05-06-2006
Detailed Design Issue
3.1
External Lighting
The Contractor shall supply and install all necessary materials and
equipment to provide a complete landscaping lighting installation
with all lighting poles/bollards, pathway lighting, spike light,
underwater lighting, recessed light and flood light projector as
shown on the drawings.
The poles shall be complete with column, doors, column root,
earthing terminal, cable entry slots, luminaires, control gear and
MCB cutout.
Page 38 of 60
05-06-2006
Detailed Design Issue
Page 39 of 60
05-06-2006
Detailed Design Issue
COMMUNICATION SYSTEM
Telephone System (Conduits, Junction Boxes and Outlets)
The telephone equipment and wiring is not included in this
contract and will be furnished by others.
The contractor shall supply and install all Q-Tel approved
manholes, manholes covers, conduits, trunking, boxes, accessories
and outlet. The contract includes for excavation, trenching laying
of ducts/conduits bends, accessories, backfilling and finishing of
all exterior line all in accordance with Q-tel Consultants
instructions.
The contractor shall supply and install telephone distribution
frame boxes as indicated on the drawings, comprised of recessed
white PVC box 300 mm. high x 400 mm. long x 100 mm. deep,
complete with hinged cover plate. Consult Q-tel planning section
for exact dimensions recommended prior to supplying the boxes.
Telephone outlets shall be of a line jack type used by the Q-tel and
to the approval of the Consultant.
Outlet boxes shall be provided where shown on drawings. Pull
boxes shall be provided according to Q-tel regulations and
wherever needed to facilitate the pulling-in of wires. All conduits
shall be provided with pull wires to facilitate pulling-in of cables by
others.
All internal telephone conduits shall be 25 mm. unless otherwise
specified. All distribution boxes shall be connected to each other
by minimum 50 mm. PVC conduits, or as shown on drawings.
All telephone outlets shall be connected to their nearest
distribution frame boxes, a maximum of 3 shall be allowed on one
radial circuit unless indicated otherwise.
PVC conduit, trunking, boxes and accessories shall comply with
the relevant clauses of these specifications.
Manhole covers for telephone manholes shall be heavy duty type
of a manufacturer and shape approved by Q-tel.
Page 40 of 60
05-06-2006
Detailed Design Issue
5.2
INSTRUCTIONS TO BIDDERS
5.3
SCOPE OF WORK
a.
Contractor's Responsibilities
The Contractor shall furnish and install all necessary software and
hardware, wiring, and computing equipment in compliance with
this specification. Any variances from this specification or related
documentation shall be submitted in writing at the time of bid.
System Requirements
b.
i)
Standard Material/Products:
All material and equipment used shall be standard components,
regularly manufactured and available and not custom designed
especially for this project
ii)
Modular Design:
The system architecture shall be fully modular
expansion of application software and field hardware.
permitting
iii)
Performance:
The system, upon completion of the installation and prior to
acceptance of the project, shall perform all operating functions as
detailed in this specification.
5.4
ii
Electrical Supply
Page 41 of 60
05-06-2006
Detailed Design Issue
The Power Supply shall operate on 240 VAC, 50 Hz, and shall
provide all necessary power for the control panel.
In the event of a mains electrical failure, the fire alarm control
panel shall have the capability of being supported in its intended
state by standby batteries. The fire alarm control panel shall be
fitted with an integral 0.7 Amp battery charger, current limited with
DDP for 24 V lead acid batteries. The battery charger must be
capable of being up-graded in capacity to facilitate larger systems.
iii
Sounder Output
A minimum of two on-board sounder circuits shall be provided. The
sounder outputs shall be fully programmable, monitored and short
circuit protected. Each circuit shall support a load of 1 Amp. with a
total panel loading of 1.3 Amps.
Auxiliary Relay
The panel shall incorporate as standard 1 x failsafe fault output and
1 x fully programmable fire output each with volt-free changeover
contacts rated at 24 V AC/DC, 1 Amp maximum. It shall be possible
to add further programmable changeover relay contacts to the panel
via the detection loop and the dedicated RS485 peripheral bus. It
shall be possible to connect up to 400 fully programmable outputs
to the fire alarm control panel in this manner.
vi
Page 42 of 60
05-06-2006
Detailed Design Issue
Page 43 of 60
05-06-2006
Detailed Design Issue
ix
Program Integrity
A program integrity option shall display the panel software version
along with ROM and RAM checksums. The RAM checksum shall
alter whenever the configuration is changed. For example, the
checksum figure shall change when either adding or removing
devices or changing text assignments. After the final configuration
has been entered the program integrity shall be checked and the
RAM checksum figure recorded.
Day Modes
The fire alarm control panel shall have the ability to automatically
invoke different operating modes according to the time of day. Each
mode shall have adjustable start and finish times. Outside of the
designated start and finishing times, the panel shall revert to
normal operation. The operating modes will consist of:
Delayed mode - During the day or night the alarm signal from the
detection points shall be immediately recognized and identified on
the panel display, but no outputs switched on until staged timers
have expired. Manual call points shall always override this mode.
Sensitivity mode - Shall allow smoke and temperature detectors to
use different pre-alarm and fire alarm thresholds during day and
night mode.
Verification mode Shall allow smoke detectors to tolerate transient
alarms according to the programmed verification delay time during
either day or night.
xi
Event Log
The fire alarm control panel shall store the last 500 events. It shall
be possible to set the event log to either "diagnostic" or "normal"
mode. Normal is the default mode.
When in diagnostic mode the log shall record every event including
single response failures from a device. The diagnostic mode shall
aid the engineer to determine spurious or transient fault conditions
including loop wiring and detector problems, particularly if these
are intermittent.
xii
Displayed Identification
During normal panel operation, when the fire alarm control panel is
operating correctly, the LCD display shall display a message that
identifies the system installer / maintenance company, this display
shall feature up to 20 characters
If a fault occurs on the fire alarm control panel the LCD display
shall automatically show a telephone number to call for assistance,
this display shall feature up to 20 characters.
05-06-2006
Detailed Design Issue
5.5
ANALOGUE
NETWORK
ADDRESSABLE
FIRE
ALARM
CONTROL
PANEL
5.6
i
Page 45 of 60
05-06-2006
Detailed Design Issue
ii
iii
iv
Page 46 of 60
05-06-2006
Detailed Design Issue
Control Module
Addressable Control Modules shall be provided to supervise and
control the operation of one conventional indicating circuit of
compatible, 24 VDC powered, polarized audio/visual indicating
appliances. For fan shutdown and other auxiliary control functions,
the control module may be set to operate as a Volt Free relay
contact.
The Control Module shall mount in a purpose made surface mount
box.
The indicating circuit may be wired for a maximum of 1 Amp
(Inductive) or 2 Amps of Resistive A/V Signal operation, or as a Volt
Free Contact (Form C) Relay. The relay coil shall be magnetically
latched to reduce wiring connection requirements, and to ensure
that 100% of all auxiliary relay or indicating circuits may be
energized at the same time on the same loop.
Audio/visual power shall be provided by a separate supervised
remote power supply.
The Control Modules shall provide address setting on the module using
decimal switches. Addressable Modules that use binary address setting
methods, such as a dip switch, code cards or soft addressing are not
acceptable. The modules shall also feature an internal identifying code
that the C.I.E. shall use to identify the type of module.
A magnetic test switch shall be provided to test the module without
opening or shorting its wiring.
vi
Isolator Module
Isolator Modules shall be provided to automatically isolate
wire-to-wire short circuits on a loop. The Isolator Module shall limit
the number of modules or detectors that may be rendered
inoperative by a short circuit fault on the loop. At least one isolator
module shall be provided at either side of each zone of the building.
If a wire-to-wire short occurs, the Isolator Module shall
automatically open-circuit (disconnect) the affected segment of the
loop. When the short circuit condition is corrected, the Isolator
Module shall automatically reconnect the isolated section of the
loop.
The Isolator Module shall not require any address setting, and its
operations shall be totally automatic. It shall not be necessary to
replace or reset an Isolator Module after its normal operation.
The Isolator Module shall mount in a standard purpose made surface
mounted back box. It shall provide a single LED that shall flash to
Page 47 of 60
05-06-2006
Detailed Design Issue
Page 48 of 60
05-06-2006
Detailed Design Issue
6.1
EARTHING
The Contractor shall provide for an adhere to QGEWC regulations
very strictly as regards earthing and bonding systems are involved.
However, the context of these regulations are highlighted briefly
as follows:
The M.V. panels connected from the transformers shall have an
earth bar of minimum cross-sectional area of 300 sq. mm. running
the full length of the panels. Removable neutral and earth links
shall be provided in the M.V. panels which shall be of a minimum
cross sectional area of 300 sq.m.
The earth bar in the m.v panels shall be connected to the earth
provided by QGEWC or with independent earth station specially
provided for this.
Where armoured cables are above ground, the armouring of the
cable shall be used as the earthing conductor and in case of
armoured cable in ground and back-filled, the armouring is not to
be used as a sole means of earthing, but additional means are
provided by either of the following :
a.
b.
The inner lead or lead alloy sheath of armoured cable i.e. in case
of PILCA or PVC.
The outer copper sheath of MICC cables may be used as the earth
conductor. This cable shall not be buried in ground directly but in
a non-metallic pipe.
In case of wiring in conduits, a separate earth conductor of PVC
copper of appropriate size shall run.
For ring main circuits, the earth conductor shall also complete the
ring.
Where a means of earthing has not been provided by QGEWC, the
consumer's earthing terminal shall be connected by the earthing
lead to an effective earth electrode or electrodes, such as copper
strip or rod, which shall be buried in the ground at a position as
near as practicable to the consumer's earthing terminal. Each
electrode shall be driven to a depth such that it penetrates the
summer water table by a minimum of 2 meters.
Every connection of an earthing lead to an earth electrode shall be
made in a pit measuring 300 mm. x 300 mm. The connection shall
be either soldered or clamped. The pit shall be filled with sand
and a removable cover placed on each pit.
6.2
BONDING
Page 49 of 60
05-06-2006
Detailed Design Issue
i.
a.
b.
6.3
WIRING
&
INSTALLATION
The Public Address & Voice Alarm System shall be installed using
1.5 sq. mm screened fire resistant cables.
Installation shall comply with the requirements of BS 5839, BS
7443 and BS 6840 part 16 and shall be in accordance with the
manufacturers recommendations.
The manufacturers recommended components shall be used for all
supports, connections and terminations. The system shall be a
standard product of one single manufacturer.
6.4
TESTING, COMMISSIONING
&
HANDING OVER:
Page 50 of 60
05-06-2006
Detailed Design Issue
Page 51 of 60
05-06-2006
Detailed Design Issue
General
The Contractor shall fully test and commission the whole of the
electrical installation in accordance with QGEWC/IEE regulations
and also in accordance with the following clauses.
The test shall be recorded in detail and the results submitted to
the Consultant. The Contractor shall then demonstrate that the
installations are properly commissioned, that they operate in the
correct manner and are capable of functioning to accomplish the
design intention as outlined herein.
ii
Site Tests
Site testing of all systems and components comprising the works
shall be carried out in the presence and to the complete
satisfaction of the Consultant after the Contractor has first
satisfied himself that the installation is functioning properly.
The Contractor shall provide all certified instruments, equipment,
plant, labour and materials necessary for conducting specified site
tests and shall be responsible for and prepared to demonstrate the
accuracy of all the test instruments supplied by him.
The Contractor shall give the Consultant, notice in writing when
any portion of the electrical installation is complete. Should the
Consultant or his representative not attend within 7 days of receipt
of such written notice, the Contractor may proceed with the test,
however duplicate certified copies of the results obtained shall be
forwarded the Consultant.
All electrical installations, plant and equipment tests shall fully
satisfy the requirements of the Ministry of Electricity and Water,
State of Qatar and those laid down in the IEE regulations as issued
by the Institute of Electrical Consultants, 15th edition.
The Contractor shall be deemed to have included in his price for
all safety devices etc., as required by QGEWC.
Once the
Contractor has satisfied himself that the installation complies with
QGEWC requirements, he shall arrange QGEWC to conduct their
own test prior to handing over. Observations shall be made of the
operation and performance of the installation and subsequent
readjustments shall be made as necessary.
Records of commissioning and testing shall be kept and when the
Contractor has satisfied himself that the installation is functioning
correctly, the results shall be comprehensively reported in a bound
copy to the Consultant.
iii
Page 52 of 60
05-06-2006
Detailed Design Issue
The Contractor shall also be held liable for any cost of dismantling
or re-erection and making good of any works which may have to be
undertaken in order to replace defective parts.
iv
Electrical Tests
Following tests shall be carried out by the Contractor.
All alarm, control and protective circuits shall be tested for correct
operation.
All lighting circuits shall be energized and checked to ensure that
they are all operational.
All single pole switches shall be checked to ensure correct polarity
and that the live conductor has been connected. Neutrals must
not pass through any switch
All motors, plant and any electrical equipment connected with
mechanical services shall be checked to ensure that they run
freely in the correct direction of rotation and that they run without
undue noise or vibration.
vi
Page 53 of 60
05-06-2006
Detailed Design Issue
viii
ix
General Commissioning
The Contractor shall:
a.
b.
c.
d.
e.
Should the test carried out fail to demonstrate that the plant and
equipment is correctly installed and/or functioning correctly, the
Consultant shall decide whether such failure is due to negligence
upon the Contractor's part (including in this context as defined all
his subContractor's and suppliers) in which case, the Contractor
shall carry out all remedial works entirely at his own expense.
Page 54 of 60
05-06-2006
Detailed Design Issue
f.
i.
ii.
iii.
Insulation resistance
iv.
Earth continuity
v.
vi.
vii.
Page 55 of 60
05-06-2006
Detailed Design Issue
Page 56 of 60
05-06-2006
Detailed Design Issue
9 SPARES
When making submittals for approval of items of equipment, the
Contractor shall include a list of manufacturer's spares for 2 years
running, further to the Warranty period. These shall be provided,
procured and supplied under this contract. Prior to order, the
Contractor shall prepare in triplicate a submittal listing all spares
for each item of equipment, clearly detailing manufacturer's name,
address telephone and telex numbers and spare part reference
number, together with component cost. The submittal shall be
passed to the Consultant for approval and only upon receipt of
approval in writing from the Consultant may the final order be
placed.
Contractor shall also provide the following spares:
-
2 sets of Fuses for each type and size used along with fuse holder.
Spare MCBs as per the DB schedule
10% of lamps of all types (min. 2 nos.)
Two set of lugs for each type & size of cable used.
1 Set of Contactor for each type of C/O Panels and Motor Control
Panels
Also the recommended spares for 2 Years standard operation and
maintenance for all the following specialized systems shall be
included procured and supplied:
a)
Page 57 of 60
05-06-2006
Detailed Design Issue
2.
ABB (EUROPE)
DORMAN SMITH, UK
MERLIN
GERIN
(FRANCE)
3.
DW-WINDSOR (UK)
4.
DISTRIBUTION BOARDS
ABB (EUROPE)
MERLIN GERIN (UK)
DORMAN SMITH, UK
CLIPSAL
5.
STROMBERG,
ABB-SWEDEN
CLIPSAL
MERLIN GERIN (UK)
6.
CABLES
CABLE
DUCAB
(UAE),
GULF
(KUWAT),
OMAN
CABLE
PYROTENAX
BICC,
(OMAN)
7.
AEI,
MICC CABLES
WREXHAM
8.
CABLE TRAY
BARTON, SWIFT
TRUNKING
ACKERMANN,
9.
G.I. CONDUITS, AND FITTINGS
BURNTUBES
BARTON,
10.
PVC CONDUITS AND FITTINGS,
EGA,
MARSHAL TUFFLEX,
DECODUCT, CLIPSAL
11.
FLEXIBLE FIRE CABLE
PIRELLI
FP
12.
WIRING ACCESSORIES
CLIPSAL
13.
FIRE ALARM & CO SYSTEM
NITIFIEL
14.
FIRE FIGHTING
Page 58 of 60
MEM,
200
MK,
GENT,
GOLD,
HAMILTON,
AUTRONICA,
05-06-2006
Detailed Design Issue
15.
16.
EARTHING
(UK)
17.
JSB, VENTILUX
W.J.
Details
of Fixture
Bollard
Light270x270x400mm high,
covered with recessed
frosted glass.
No.
of
Lam
ps
1
Sock
et
Type
Control
Gear
IP
Min.
B15d
Integral
Electro
nic
68
G24d
-1
Integral
Electro
nic
65
GY
6.35
Integral
Electro
nic
67
18W
TC-D
G24d
-1
Integral
Low
Loss
657
150W
HIT
G12
Integral
Electro
nic
20
TCDEL
18w
G24q
-2
Integral
Electro
nic
667
Page 59 of 60
Light
Sourc
e
23W
TC-D
05-06-2006
Detailed Design Issue
thermal shock.
G
Page 60 of 60
12V75W
GY
6.35
HF
Integral
Electro
nic
68
25W
QT 14
GY
6.35
HF
Integral
Electro
nic
68
05-06-2006
Detailed Design Issue