Surface Grinding Machine Maintenance Schedule For Weekly Intervals
Surface Grinding Machine Maintenance Schedule For Weekly Intervals
Manufacture:
TASK
WEEKS
1 st week
2 nd week
3 rd week
4 th week
Mechanics Signature:
Date:
Model:
LUBRICATE THE
COLUM GREASE
FITTING WITH TWO
PUMP OF GREASE
Month:
VACUUM METAL
SHAVINGS FROM
MACHINE
CORRECT ANY
UNSAFE CONDITION
TASK
MONTHS
January
February
March
April
May
June
July
August
September
October
November
December
Mechanics Signature:
Date:
INSPECT FOR
CHECK INSOLATOR IS
DAMAGE TO SWITCH
LOCKABLE IN OFF
GEAR, WIRING AND/
POSITION
OR CONDUIT
Model:
CHECK OPERATION
OF START/ SWITCH
Year:
CHECK EMERGENCY
STOP WHERE
FITTED
Model:
TASK
CLEAN MACHINE
OFF ALL FOREIGN
MATTER
YEARS
2015
2016
2017
2018
Mechanics Signature:
Date:
CHECK THAT
WHEELS ARE NOT
CHIPPED,
CLOGGED,
GLAZED OR
CRAKED
CHECK
OPERATION OF
QUICK CHANGE
GEAR BOX IS
FITTED
LUBRICATE WAYS
AND SLIDES
REPLACE
COOLANT
CORRECT ANY
UNSAFE
CONDITION