Project Profile of:

Location:
Developer:
Contractor:

Vinia Residences Project


EDSA, West Triangle, Quezon City, Philippines

Filinvest Land
Archipelago Builders

Project Manager: Engr. Noel

Gayos
General Project Details:
The Vinia Residence Project is designed as a wall and slab structure, a preferable
building design by Filinvest Land to develop Buhos, Tibay structures, a seal of
quality for its clients.
FASI Scope of Work:
Archipelago Builders, contractor of Vinia Residences Project contracted with FASI to
supply its Aluma Easy Set, an all aluminum modular panel form system for monolithic
cast-in-place concrete construction. It covered the full external walls, window, ACU
openings and the ledge for the ACU. It covered the staircase with nosing and casted
together the angular steel step guard. All of the structural shear partition walls, Core
Wall and slab were cast-in-place monolithically together with the external walls and
staircase. The operation of 1 time casting also included the electrical works, boxes
and plumbing imbedded in the partition walls.
Archipelago only provided form oil, tools for workers and Pipe and clamps for safety
rails and C-purlins with plywood for catwalk.
The structures for the basement and podium were irregular and of different elevations
and Archipelago utilized the use of Loose Forms and Table Forms. Aluma Easy Set
was used for the Typical Floors from Level 2 to the Roof Deck.
The Typical Floors totals to 26 typical levels where the half-floor set of Aluma Easy Set
were used twice per floor for a total uses of 52 times. The form cycle averaged at 4 to
5 days per cycle for each half-floor set or averaged at 10 days per floor or 3 floors per
month.
Performance and Productivity:
Formwork Crew were 38 workers employed at 10 hours work each day for a total
manhours of 380 hours. Total number of days of formworks is 3.5 days. Total
manhours 380 x 3.5 days Totals 1,330 manhours. Total Form area is 2,116. Average
sq. mtr per manhour is 2116/1330 Total 1.59 x 10 hours or 15.9 sq. mtrs per
manday.