PKSDE shall be responsible to perform or cause to be
PKSDE Tie-In Work and Obligations. F
performed and shall be responsible for any andi all costs in relation to:
A
the survey, design, specification, engineering, procurement, construction of fiscal
metering, Emergency Shutdown Valves (ESDVs). pig launcher and connecting pipeline
from fiscal metering at Senipah Facility to Power Plant (Connecting Pipeline") wth all
accessories, appurtenances and supporting equipment as described in Exhibit 1
subject to approval of TOTAL;
the asset integrity of the above-mentioned facilties under Article 2.2 A including the
maintenance and inspection during the term of this Agreement,
the tie-in of the Connecting Pipeline to Buyer's Facilities outside Senipah Facility;
the identification of, application for and the obtaining and maintaining of necessary
permits, licenses, nghts of way, government approvals, and any third party consents
with respect to performance of PKDSE under this Article
the Pre-commissioning PKSDE Tie-In Work of the above-mentioned facilities under
Atticle 22 A as well as Connecting Pipeline pre-commissioning which consists of
cleaning; dewatering and optional swabbing; drying and flushing the pipeline;
stabilization at the final dew point; and filing with nitrogen and inerting (when required)
TOTAL shail, in accordance with the Standard of a
TOTAL Tie-In Work and Obligations,
Reasonable and Prudent Operator, be responsible to perform or cause to be performed and
‘shall be responsible for any and all costs in relation to:
A
B.
the hot tap tie-in to existing 36° main gas pipeline;
the design, specification, engineering (design, studies and review) of Tie-In Facilities
as per TOTAL standards and specifications;
the design, specification, engineering, procurement, construction of isolation valve,
including Process Shut Down Valve (‘PSDV") and flange for metering skid with all
accessories, appurtenances and supporting equipment as described in Exhibit 1;
the asset integrity of the above-mentioned faciities under Article 2.3 A, B and C
including the maintenance and inspection during the term of this Agreement,
the personnel allocation to supervise the quality assurance and quality control of the
material procured ty PKSDE and the production of the final document dossier and pre-
commissioning dossier, in relation to the Tie-In Facilities:
the identification of, application for and the obtaining and maintaining of necessary
permits, licenses, rights of way, government approvals, and any third party consents
with respect to performance of TOTAL under this Article 2.3;
the Pre-commissioning of TOTAL Tie-In Work of the above-mentioned facilities under
Atticles 2.3 A and G;
the Commissioning in coordination with PKSDE; and
in coordination with PKSDE, perform the baseline intelligent pigging after the
commissioning as part of quality assurance of Buyer facilities.34
32
Costs under Articles 2.2 and 2.3, PKSDE shall be responsible for all costs and charges
‘associated with the activities as described in Article 2.2 and TOTAL shall subject to Articles
7.2 and 7.4 herein be responsible for all costs and charges associated with the activities as
described in Articles 2.3 except Article 23 E
‘Other Costs. PKSDE shall be {uly responsible for any costs incurred due to activities outside
the scope of TOTAL Tie-In Work and shail reimburse all actual costs and charges incurred by
TOTAL in the event TOTAL is forced to cary out activities other than those governed by this
Agreement but in the judgment of TOTAL as Reasonable and Prudent Operator are required
to support the Tie-In Works including in emergency situation during the performance of the
Tie-In Works which emergency situation will be notified immediately by TOTAL to PKSDE.