Initial Stage

All slum dwellers residing on the plot prior to 1/1/1995 and are in use of
the structure are eligible for rehabilitation.
1.At least 70% of the slum dwellers in a slum unite under a slum dwellers cooperative housing society.
2.They appoint a chief promoter. Collect share capital of Rs. 50/- per member and
Re. 1/- as entrance fee. This is then deposited in the name of the proposed housing
society in the Mumbai district central co-operative/ Maharashtra State co-operative
bank ltd.
3.Documents regarding the title of the land are collected by the society. The plot is
got measured and the slum structures are properly demarcated.
4.of structures on the plot is carried out and the structures are numbered on the
plan. A table of house number as per plan and the name of the occupant is
prepared.
5.A suitable developer is appointed by the society by a general body resolution. The
developer appoints professionals like Architect/ Licensed surveyor; Structural
engineer; etc.
6.The developer enters into individual agreements with all the slum dwellers
agreeing to participate in the scheme.
7.A proposal enclosing requisite plans; annexures and documents is submitted by
the architect to SRA.
Second Stage

1.
2.
3.
4.
5.
6.
7.

Initial scrutiny of the proposal is carried out by the concerned sub-engineer. It is ensured that a
documents are submitted along with the proposal.
If the proposal is in order, the amount of scrutiny fee to be paid is worked out by the sub-engin
The scrutiny fee is paid by the developer.
Annexure II is forwarded to the competent authority for certification.
Annexure III is simultaneously forwarded to the financial wing for scrutiny.
Annexure I is scrutinized by the engineering wing.
After Annexure II & III are certified by the competent authorities, approvals to LOI, layout. In
Approval and commencement certificate to the first building for work upto plinth are processed
is made to issue all these four approvals at one go, at-least for the first rehabilitation building.

Third Stage

1.
2.

The society draws lots for allotment of the tenements to the members who are ready to pa
the scheme. Draw for the non- participating members from the remaining tenements is als
The developer arranges for transit accommodation to the slum dwellers, which can be eit
or off site, as mutually agreed between the slum dwellers and the developers.

3.

4.
5.

6.
7.
8.

1.
2.
3.
4.
5.
6.
1.
2.
3.
4.

In case the developer has difficulty in arranging for suitable transit accommodation,
constraints, SRA extends all help to the developers to locate suitable site in the
construction of transit camps and helps to obtain permissions from concerned authorit
same. In case no suitable site is available in the vicinity, transit camps of MHADA, MMRD
be taken on rental basis by the developers.SRA extends all possible help for obtaining th
tenements from these authorities.
Draw of lots for allotment of transit tenements is drawn.
The slum dwellers are shifted to the transit camps and their hutments demolished. The slu
who do not agree to participate in the scheme are given notice by the society stating the
details and requesting them to participate in the scheme.
If these members do not agree to participate within 15 days of the approval of the propos
physically evicted from the site under the provisions of Sec 33 & 38 of Maharashtra S
(Improvement, Clearance and Redevelopment) Act, 1971, to ensure that there is no obs
the scheme.
After demolition of the structures, work upto plinth is completed.
After checking the plinth dimensions, further permission to carry out construction beyon
granted.
Fourth Stage
Plans for the further buildings both for sale and rehabilitation are then approved.
Building permissions for the sale buildings are given in the proportion of the permissions g
rehabilitation buildings.
Upon completion of rehabilitation building/ wing, list of allotment is drawn up. The allotm
in the joint name of the head of the household and the spouse.
Building completion certificate is submitted by the architect.
After checking of the building and compliance of the IOA conditions Occupation permis
building is granted. The slum dwellers as per the allotment list are given possess
tenements.
SRA issues identity cards to the slum dwellers.
Fifth Stage
Further construction of the remaining building/s is then taken up.
Further building permissions as well as occupation permissions to the buildings is then
due course.
Upon completion of the last buildings in the layout, the underlying land is transferred on l
society of slum dwellers. In case of Government lands, the lease rent is nominal.
Separate property cards for the rehabilitation building plot and the sale building plot as
the reservation plots to be handed over are prepared. SRA acts as facilitating agency in c
difficulty with the revenue authorities.