Brief Report On Emergency Shutdown Wef 25
Brief Report On Emergency Shutdown Wef 25
Action taken:
1.
Replacement of R phase Lightning arrestor , Surge counter by new
one.
2.
Dismantling , cleaning , refurbishing , reassemble of the Generator
Field Breaker.
3.
Connection of the earthing conductor at Tail race end.
4.
Overall inspection of the Generator Transformer , Lines from
Generator Transformer yard to Switch Yard , Switching equipment,
Relays panel.
5.
Break Down Voltage of Transformer Oil as on 26.11.2014.
Radiator
: Average 30KV
Tank bottom
:Average 31KV
Tank top
:Average 32 KV
6.
Oil Filtration starts at 9:30 hours of 28.11.2014.
7.
Oil Filtration stops at 5:30 hours of 2.12.2014.
8.
Final test of Transformer Oil on 2.12.2014.
Average BDV :43KV.
9.
Insulation Resistance value of GT-II in Mega Ohms as on 2.12.2014.
HV LV
HV E
LV E
R15 Secs
R60Secs
8000
9000
6000
8000
4000
5000