A. On running with load of 30 MW , the Unit-II machine of stage-III power
Station tripped at 16:52 hours on 25.11.2014 .
Affect of the tripping :1. R phase Lightning arrestor blasted.
2.Burn out of the Generator Field Breaker.
Indication:
ENLO , ELO , Gen.Tr.REF Prot trip , Gen 2nd Rotor Earth fault trip.
RET 670: General trip , REF protection.
Relays operated:
86A , 86B , 51VAX , 51VCX.
B.

Action taken:
1.
Replacement of R phase Lightning arrestor , Surge counter by new
one.
2.
Dismantling , cleaning , refurbishing , reassemble of the Generator
Field Breaker.
3.
Connection of the earthing conductor at Tail race end.
4.
Overall inspection of the Generator Transformer , Lines from
Generator Transformer yard to Switch Yard , Switching equipment,
Relays panel.
5.
Break Down Voltage of Transformer Oil as on 26.11.2014.
Radiator
: Average 30KV
Tank bottom
:Average 31KV
Tank top
:Average 32 KV
6.
Oil Filtration starts at 9:30 hours of 28.11.2014.
7.
Oil Filtration stops at 5:30 hours of 2.12.2014.
8.
Final test of Transformer Oil on 2.12.2014.
Average BDV :43KV.
9.
Insulation Resistance value of GT-II in Mega Ohms as on 2.12.2014.
HV LV
HV E
LV E

R15 Secs
R60Secs
8000
9000
6000
8000
4000
5000

Instrument used : WACO 5000 Volts Megger.


Time
:13:30 hours
WTI
:25 deg Cent.
OTI
:26 deg cent.
Weather
:Sunny.
10.

The machine was synchronised to the grid after observing all


formalities at 20:15 hours of 2.12.2014.