Monthly Report 01 Saad
Monthly Report 01 Saad
Monthly Report 01 Saad
REPORT NO.
NAME :
01
Muhammad Saad
DESIGNATION:
Management Associate
P. NO. :
APP. BATCH:
1921
19
.
.
TO : TRAINING MANAGER
THRU :
/ __________.
UM
/ Deptt. Mngr.
During the above mentioned period, I was in Machinery Ammonia and involved in following
jobs.
Self study:
Ammonia Plant:
Complete pump replacement of G-206-A (Benfield Lean solution pump) with a spare
one to rectify the mechanical seal leakage problem.
Mechanical seal replacement of G-207 (Side stream carbon filter pump) to rectify the
mechanical seal leakage problem.
Replacement of MV motor (GM-206-A) with spare one preventively.
D-402 agitator modification activity to rectify the high vibration problem.
Replacement of GM-301-A motor due to high vibration
Gland packing replacement G-405-B (Phosphate Dozing Pump) to rectify the leakage
problem.
Involved in the startup activity of K-101-B (Air compressor).
Routine preventive maintenance of small machines.
Greasing of EM-215 A/B and EM-216 A~D.
DAP Plant:
During DAP plant shutdown involved in following jobs,
Pre-turnaround activities:
SAP: