Inspection and Test Record For Power Transformer: Record No.: - Page 1 of 2

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Record No.

Inspection and Test Record


for Power Transformer

page 1 of 2

Client:

Subcontractor:

Project No.:

Subcontract P.O. No.:

Project Name:

Substation No.:

Additional Information:

Rating: ...................................... kVA

Manufacturer::

Vector group:

P.O. No.:

Voltage: ..................../.................... V

Current: ..................../.................... A

Location
Serial No.:

Reference Document:
Subcontractor

Items to inspect

inspected
initials/date
1.0

Company
Hold
Point

Remarks

inspected*
initials/date

Inspection of the switchgear transformer


feeder unit
Completed:
Form No.:
Protection relay setting:

2.0

Insulation resistence tests:

3.0

HV winding to earth ...,,.....

.........

.........

LV winding to earth ...,,.....

.........

.........

HV to LV winding

.........

.........

...,,.....

Earthing
Check the condition - neutral earthing
Measure:
neutral earthing continuity
........................ Ohm
equipment earthingn continuity
........................ Ohm

4.0

For breathing type transformers:


- check the position of the conservator valve
- check the silicagel condition/color
- result of the oil test main tank/conservator
- test gas/oil relay (buchholz) alarm/trip
- check termometer .................. reset max.
indicator

H - Companys presence is mandatory for all activities in section.

Attachments, No. of pages:

h - Companys presence is mandatory.

Accepted for Subcontractor


Name:

Signature:
Date:

Accepted for Company


Name:

Signature:

Date:

Accepted for Client


Name:

Signature:

Date:

*Company only initials for holdpoint

C:\RB_Forms\RB26E16.DOT\

www.red-bag.com

Record No.:

Inspection and Test Record


for Power Transformer

page 2 of 2

Client:

Subcontractor:

Project No.:

Subcontract P.O. No.:

Project Name:

Substation No.:

Additional Information:

Rating: ...................................... kVA

Manufacturer::

Vector group:

P.O. No.:

Voltage: ..................../.................... V

Current: ..................../.................... A

Location
Serial No.:

Reference Document:
Subcontractor

Items to inspect

inspected
initials/date
5.0

Company
Hold
Point

Remarks

inspected*
initials/date

Check single core cable bonding


(for pre-commissioning inspection only)

6.0

Inspection of the electrical system of cooling


fans/pumps

7.0

Basic inspection completes


Sheet No.:

8.0

Remedial action completed:

H - Companys presence is mandatory for all activities in section.

Attachments, No. of pages:

h - Companys presence is mandatory.

Accepted for Subcontractor


Name:

Signature:
Date:

Accepted for Company


Name:

Signature:

Date:

Accepted for Client


Name:

Signature:

Date:

*Company only initials for holdpoint

C:\RB_Forms\RB26E16.DOT\

www.red-bag.com

You might also like