AMPE (LUMUT) OPERATIONS WEEKLY REPORT

Page 1 of 3
Rev. 00

GENERAL INFORMATION
24th November

25

th

26

th

2014 ( Monday )

24 Axle Line c/w ppu x 2 units (Bechtel Deck ) (Additional )

November

2014 ( Tuesday )

12 Axle Line x 2 units Coolers Shifting

November

2014 ( Wednesday)

12 Axle Line x 2 units Coolers Shifting

12 Axle Line x 2 units Coolers Shifting

27th
28

th

29

th

30th

November
November

2014 ( Thursday )
2014 (Friday)

12 Axle Line x 2 units Coolers Shifting

November

2014 (Saturday )

Preparation 18axle c/w PPU x 2 ( Bechtel Deck ) ( Additional )

November

2014 (Sunday)

18 Axle Line c/w ppu x 2 ( Bechtel Deck ) (Additional)

UPCOMING EVENTS/ACTIVITIES
Long Term Lumut Operations

30/11/2014 -6/11/2013/- 101DA Main Deck 1 , 2 ,3 ,4

MAINTENANCE STATUS

On-going Repair/Maintenance:

Long Term Trailers In Maintenance A & B Services.


SL-E Power Pack Repair Works
Ballast Pump Refurbishment

Attachments
REV: 00

Tracing No: AMPE-Nov-04

AMPE (LUMUT) OPERATIONS WEEKLY REPORT

Page 2 of 3
Rev. 00

Coolers Shifting 12 Axle Line

Coolers Shifting 12 Axle Line

Coolers Shifting 12 Axle Line

Coolers Shifting 12 Axle Line

Coolers Shifting 12 Axle Line