With reference of M/s Hyder Safety Inspection Ref No.

62 herewith attached corrective


action which are implemented at site.
Picture no. 5 Access ladder placed in safe way and secured enough to protect the people
from falling.

Picture no. 6 Given TBT to the workers about the Importance and usage of PPE. Find the
attachment.

Picture no. 7

Picture no.08

Picture no 09

Picture no 10

Picture 11

Picture no. 7 the lifting accessories are collected stacked in a particular area

Picture no. 8 the empty fire extinguisher are replaced with a new one
34
Picture no. 9 edge protection provided with concrete barriers
Picture no.10 to avoid tripping hazard gravel filled, also ladder anchored to the wall.
Picture no. 11 boulders are removed from there
Picture no. 12 provided out rigger pad for the cranes for safe lifting
Picture no. 13 given TBT to all riggers about the importance and usage of PPE. Find the
attachment
Picture no. 14 maintained proper housekeeping and the material are collected and kept in
a safe place
Picture no. 15 provided public protection and installed gate
Picture no. 16 Picture no. 17 maintained proper housekeeping and the scattered materials
are collected and stored in a particular area
Picture no. 18 the damaged pressure gauge is replaced with new one
Picture no. 19 closed the ladder and provided with sing board
Picture no. 20 replaced the damaged one and provided new one