3G SSV DT Purpose Process
3G SSV DT Purpose Process
Page 1
Review
This guide defines the prerequisites, workflow,
deliverables and checklist deliverables for radio network
single site verification service. It aims to guide the
related service delivery departments and personnel to
get familiar with the service delivery content and to
deliver the service by following the standard flow, thus
delivering the service with a high efficiency and a good
quality.
Purpose of SSV DT
Page 3
Prerequisites
Page 4
Prerequisites
Site Status Audit
Before SSV test, information about Site Status must be confirmed from the RNC engineer.
The target for site status audit is to make sure the test site is working normally, otherwise it
must influence SSV. It includes:
- Alarm audit; (pay attention to transmission related alarms)
- Cell status;
- HSDPA/HSUPA status
- Neighbor list checking (if handover is required to be test)
- Basic parameters
Parameters Audit
Before SSV, the test engineer must get the configuration file and audit it.
Page 5
Workflows
Equipment Installation
Commissioning &
Implementation
System
Parameters Audit
Tools Setup
Verification Test
SSV Control
Table
Troubleshooting
Problem
Found?
N
SSV Report
Generation
SSV
Report
Radio Network
Tuning
Page 6
Workflows
Page 7
Page 8
Test Case
Category
UE #
Terminal Configuration
Configuration Details
MS1
Scanner
MS2
Short Call
MS3
Long Call
Dynamic
R99 UL/DL
MS4
3G
Ping
MS5
Video Call
MS1
MS2
Category VI (HSPA)
MS3
MS4
Category X (HSPA)
Static
Page 9
Checks
(OK/
NOK/NA)
PS
PS detach is checked
PS PDP activation and deactivation is checked
Soft handover for voice service to and from the 3G cells checked OK
Handover
Page 10
Comm
ent
Check
(OK/
NOK/NA)
Checks
Confirm Site is on -air and no alarm on site.
Check with Neighbor Relation table
General
Dedicated Mode
Voice Quality
Silent call
Page 11
Comm
ent
Types of SSV DT
In 3G DT, we have to perform two types of test
Statistic Test: In static Drive test, we have to go one by one in each sector around
100m & we choose better Level(RSCP & Ec/Io),after that we start static test. Static Test
Means without moving in sector we have to do our work.
Dynamic Test/Moving Test: In the dynamic drive test we have to move the each sector
with Genex Probe connect and record its values of RSCP & Ec/No. The Value of RSCP
& Ec/No should be good. In dynamic Drive test we have to test Coverage, quality and
Handovers of all the sectors in Long call. Long Call:- Long call means continuous call
on testing number.
Page 12
DT KPI
CLASSES
INDICATORS
SERVICES
PS DL throughput
in R99 for FTP
Transfers
PS UL throughput
in R99 for FTP
Transfers
Data
Performance
PS DL FTP
Throughput for
HSDPA (UE
Category. 6, 10 ,
20) (FTP); TCP,
window size =
256k
Successful
Completion rate
Category 20
Category 20
Page 14
Page 15
Page 16
Page 17
Now you
are ready
for DT.
Page 18
Page 19
Before starting the test, we have to lock the frequency which we want to test form Test
+ Forcing Function + WCDMA forcing features as follows(bellow left side snapshot).
After reaching the site we try to test the stationary test within 100m of every sector of
the site. For stationary test in idle we record a log file by Pressing f5 and check the
PSC, cell ID and other parameter in Basic Information window of Genex probe for
MS2(bellow right side snapshot)
Page 20
After that we collect a log for cell selection and reselection in idle mode by moving
clockwise and anticlockwise of the site. Cell selection-reselection command shows in the
signaling tab into event list window(bellow left side snapshot).
After completing the stationary test we start the connection test for MS3. For MOC and
MTC we use MS3 for MOC and MS2 for MTC for Voice call. In connection we check the
RSCP, Ec/Io from basic window into Active set. We can see the UL power from the
Power control window form basic information(bellow right side snapshot)
Page 21
Page 22
Page 23
13. In Cell reselection test in PS mode, first we have to connect internet by the dialup then
we can check this test by browsing.
HUAWEI TECHNOLOGIES CO., LTD.
Page 24
Page 25
Useful Plots
Page 26
Page 27
Page 28
Report Generation
Once the test result is acceptable and problems are solved, generate the SSV Report.
Report format will be as per operator demand.
Page 29
Rx
Rx
Tx/Rx
An
te
nn
aB
Tx/Rx
Rx
Tx/Rx
Rx
Tx/Rx
An
te
nn
aA
An
te
nn
aB
An
te
nn
aA
Sector_A
Sector_B
Right
Sector_A
Sector_B
Wrong
Page 30
Thank You