Revised Planning of Piperack As On May-22

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

PIPE RACK & CABLE RACK BALANCE WORK

Area

Description

Civil
Area Under Supervision
Drg. No.

Structural
Drg. No.

North Side of Ware House

Mr.santosh

708

736/737

L & T Cylo to Ducon febrication yard.

Mr.santosh

753

773/774

Mr.Niraj.

756

781 / 782

753

773/774

PART A

North Side Cast House Substation

PART B

M.B.E TO Cooling tower

Mr.santosh

Part C

Behind ABF ie west side of ABF gable


end towards fuel storage tank

701

Part D

ABF bldg towards ARS sub st cable tray


& cross over towards bathrecyle unit

754

Part E

West side of potline B & A

701

Part F

west side of potline A towards ETP

706

Part G

sub st Compressor house towards cast


house furncase bay

751

TOTAL

NOTE:- ABOVE REQUIREMENT

RACK BALANCE WORKS PLANNING FOR CIVIL & STRUCTUAL WORKS


Balance
Balance Completed
Erection
Erection
Pedastal Fab. (MT) Target Date
(MT)

Civil Target

Balance
Foundation

10

10

clear

28.05.12

18

18

42

22

clear

30.05.2012

05.05.2012

15

clear

12

30.05.2012

12

clear

Remarks

25

30.05.2012

25

41

41

27

38

80

15.05.2012

80

43

49

100

15.05.2012

100 Area not clear

20.06.2012

30

33

130

30.06.2012

130

122

147

440

TOTAL

NOTE:- ABOVE REQUIREMENT SHOULD BE PROVIDE TIMELY.

435

Area not clear

Area not clear

IVIL & STRUCTUAL WORKS


Remarks

Hurdles

Complete

3nos of foundation &


pedastal are balance, which
are coming in hard rock
area. Required breaker for 4
days to complete the task

Complete

Due to Hard
Rock & R/F

LY.

Metalling & PCC work in


progress at gable end.so
southwest corner footing
with 6 nos of pedastal
cannot be taken up.

Non available
of structural
steel so only
9ton
completed
out of 25ton

Complete

hard rock, so we need the


blasting But A little area of
Footing depth is more than
two times from drawing
level.

fabricaton
works
completed

Area greading require.


Blasting require, breaker for
ten days pokland for daily
two hours for ten days for
thirty footing,201
rmt.length ,3000cum
.quantity.

fabricaton
works
completed

You might also like