SNAG LIST OF THE MECHANICAL WORKS

No.

ITEM

1 Warning signs of U/G pipes not provided


2 The type of fire hose reel not provided as per the approved
3 The accessories of the fountain not delivered yet

Remarning Works
4 The fountain should be handedover by the supplier
5 FM200 system should be handedover by the supplier
6 Adjust the trench grate with the ground at the pump room
7 Submersible pump of the external works should be tested
8 Irrigation system not tested yet
9 Adjust the valve's spindle boxes with the road
10 Adjust the smoke grille with the wall
11 Training the client team on mechanical system
12 Waranty certficates of mechanical works
13 Spare parts

DEDUCTION
15000
7000
3000

WORKS
HOLDING