(d) Level the resources and determine the new project duration and critical path:
After leveling the resources, the critical path of the project is shown below and the duration of the
project is 21 days.
(e)Alternative solutions:
More resources can be allocated to this project to finish it on time. Set resource X and W at 200%. In
that case the project will be done on time and do not over-allocate the resources.
Problem 2
Without any resource leveling:
(a)
Set Resource at 2000% units
Solve without activity splitting (level with slack only)
(b)
Set Resource at 3000% units
Solve with activity splitting (and level with slack only)
(c)
(d)
Solve for resources at 1500%
(e)
Resources at 1500% and the project must be done in 20 days.
The amount of overtime that will have to be scheduled is 21 days.