Progression February March April May Week 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Preparation and Planning

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Progression

Week
Preparation and Planning
Choosing Designing Plant Title (Polyvinyl Chloride)
Discuss title with lecturer
Progress Report 1
Discuss task of title given
Study objectives of PVC designing
Develop scope study of PVC designing
Progress Report 2
Discuss Process Background of PVC
Finding Market Survey of PVC
Develop Project Feasibility Study and Site Study
Study Review And Screening of Alternative Processes of PVC
Determine physical and chemical properties of PVC
Progress Report 3
Develop Process Modeling and Flow sheeting of PVC
Develop Process Flow Diagram of PVC
Determine material balance based on modeling
Progress Report 4
Develop process energy intergration
Progress Report 5
Study of waste treatment and waste minimization
Study type of pollutant and government specification demand
Estimating size and cost for water treatment plant
5.0 Gant Chart

February
2 3 4

March
1 2 3

April
2 3

May
2 3

Progress Report 6
Calculate and estimating equipment sizing and costing of overall
process
Progress Report 7
Determine Process Control used in PVC Designing
Progress Report 8
Study Process safety in PVC designing
Determine general process safety procedure, plant startup and
shut down and HAZOP study
Progress Report 9
Develop mechanical design of major equipment
Progress Report 10
Finding profitability analysis design of PVC
Progress Report 11
First draft report submission
Progress Report 12
Final draft report submission