Example Project Program For Design Planning Purposes
Example Project Program For Design Planning Purposes
Example Project Program For Design Planning Purposes
01-Feb
Week 5-6
Week 7-8
01-Mar
01-Apr
01-May
01-Jun
Week 9-10 Week 11-12 Week 13-14 Week 15-16 Week 17-18 Week 19-20 Week 21-22 Week 23-24
Duration
1
2
3
4
5
6
7
8
Project Activity
Client liaison to fix the scope of works.
Obtaining of all required information.
Appointment of sub consultants for EIA and HIA
Survey for as-built information
Study of the relevant supply authority specifications.
Preliminary design for TEF presentation and approvals.
Survey and Pegging of the design
Drafting of the final design reports
2 weeks
4 weeks
2 weeks
8 weeks
4 weeks
8 weeks
12 weeks
4 weeks
01-Jul
01-Aug
01-Sep
01-Oct
01-Nov
Week 25-26 Week 27-28 Week 29-30 Week 31-32 Week 33-34 Week 35-36 Week 37-38 Week 39-40 Week 41-42 Week 43-44
Duration
1
2
3
4
5
6
7
8
Project Activity
Client liaison to fix the scope of works.
Obtaining of all required information.
Appointment of sub consultants for EIA and HIA
Survey for as-built information
Study of the relevant supply authority specifications.
Preliminary design for TEF presentation and approvals.
Survey and Pegging of the design
Drafting of the final design reports
2 weeks
4 weeks
2 weeks
8 weeks
4 weeks
8 weeks
12 weeks
4 weeks