Aim FM Work Order Reconciliation Process
Aim FM Work Order Reconciliation Process
of
Texas
at
Dallas
Parking
&
Transportation
Department
April 2015
April 2015
Figure 3
5. In the BIRT Report Viewer Parameter Box that will pop up (in a new webpage tab) enter the following:
a. Under Work Order: Enter/Find WO # found in Reconciliation Line item
b. Phase: All
c. Status Parameter Group Leave as is
d. Billing Dates: Any
e. Funding Group: All
f. Billing Amount Options: All
6. Hit Enter
April 2015
Figure 5
7. Use the Bill Report that comes up to find the amounts billed under Contract, Material, Labor, or Billed and
match it with the amounts in Reconciliation to find the correct WO Phase.
Figure 6
8. Return to the Work Management page (Figure 1) in the first tab and click on Work Order.
April 2015
Figure 7
9. On the Work Order page that comes up, click on the magnifying glass in the upper right hand corner under
About.
Figure 8
10. Copy & Paste the WO# from Reconciliation in Step 1 or from the BIRT Report in Step 6 into the Work
Order = blank. Do not fill in any of the other blanks.
11. Click on the magnifying glass in the upper right hand corner again.
April 2015
Figure 9
Figure 10
13. Click the appropriate Phase Number that you found in Step 7, Figure 5 that matches the correct billed
amounts.
Figure 11
14. Click the View dropdown menu and select Cost Analysis.
April 2015
Figure 12
15. Verify that the Total Cost matches the records in Gemini Financials
16. Screenshot the Phase page that comes up with the Cost Analysis
17. Copy the Screenshot to a Word Doc
18. Save the Word doc to the Shared drive under Billing ! FM Work Orders
19. Also save a copy to the Shared Drive under the Correct FY Year Acc Files: Billing ! FY Year Acc Files !
Period #X ! FM Work Orders
Figure 13
20. Once all the Gemini Financials Work Order line items have been accounted for and documented on the
shared drive, return to Gemini Financials and click Reviewed.