Air compressor packages.

Activities.
Checks prior to pre commissioning.
COMPLETION OF THE FOLLOWING APPLICABLE TEST
PACKAGES.
1. Electrical test packages.

Status.

1.1. Two Nos. of HV motors.

Under
progress.

1.2. Two Nos. of LV motors.

Under
progress.

1.3. One No. of air dryer packages.

Under
progress.

2. Mechanical test packages.


2.1. Piping test packages (interskid pipings
upto the receivers.).
2.2. Air compressor packages.

By PLPL/ vendor
as per the
formats.
By PLPL/ vendor
as per the
formats.
By PLPL/ vendor
as per the
formats.
By PLPL/ vendor
as per the
formats.

Completed.

By PLPL.

Under
progress.

By PLPL/ vendor
as per the
formats.
By PLPL/ vendor
as per the
formats.
By PLPL/ vendor
as per the
formats.

2.3. Air dryer packages.

Under
progress.

2.4. Air receivers.

Under
progress.

3. Instrumentations test packs.


3.1. Loop folders for the instruments inside
the skids.

Under
progress.

3.2. Loop folders for the inline instruments


on headers.

Under
progress.

Pre commissioning activities.


1. Pre commissioning checks as per the
checklists.
2. Electrical.
2.1. There is no no load tests for the HV
motors. However, a 4 hrs. full load tests
for the HV motors will be carried out as
part of performance testings.
2.2. The high voltage megger tests for the

Responsibilities.

Under
progress.

By PLPL/ vendor
as per the
formats.
By PLPL/ vendor
as per the
formats.
By vendor.

motor windings had been carried out


during the FAT. The reports will be
included in the test packs as reference.
2.3. HV/ LV motors rotational checks.
3. Mechanical.
3.1. Air blowing reports for the interskids
pipings.
4. Instrumentations.
4.1. Loop checkings for the instruments
within the skids.
4.2. Loop checkings for the instruments
inline on the headers.
4.3. Functional checks & interlocks.
Commissioning activities.
1. Compressor packages.
1.1.
Performance tests for the compressor
1.
1.2.
Performance tests for the compressor
2.
(4 hrs. continuous full load runs as part of the
performance tests.).
2. Air dryer packages.
2.1.
Performance tests for the air dryer
packages.

By vendor.
By PLPL.

By vendor.
By vendor.

By vendor.
By vendor.

By vendor.