2G Swop Preparation: 25 Sites Ready Transmission MSS Site Creation ISP BSC Acceptance Acceptance KPI Document
2G Swop Preparation: 25 Sites Ready Transmission MSS Site Creation ISP BSC Acceptance Acceptance KPI Document
Pre-requisites
25 sites ready
Transmission
MSS site creation
ISP
BSC Acceptance
Acceptance KPI document
Swop Schedule
Schedule stategy - CBD last
Schedule
Swop Process
To be discussed
2G Swop Process
Estimated downtime per sector is 1 hour.
Time
08H00
Task
Sector 1
Huawei to switch off 1st sector
NI team to pull down existing Huawei antenna
New Nokia antenna to be installed at same height and azimuth as Huawei antenna, tilts to be as per design
Sector to be unlocked and brought on air
1st CS and PS call by NI team
Responsible party
Name
Huawei
Nokia
Nokia
Nokia
Nokia
Taworn
Taworn
Amit
Taworn
Sector 2
Huawei to switch off 1st sector
NI team to pull down existing Huawei antenna
New Nokia antenna to be installed at same height and azimuth as Huawei antenna, tilts to be as per design
Sector to be unlocked and brought on air
1st CS and PS call by NI team
Huawei
Nokia
Nokia
Nokia
Nokia
Taworn
Taworn
Amit
Taworn
Sector 3
Huawei to switch off 1st sector
NI team to pull down existing Huawei antenna
New Nokia antenna to be installed at same height and azimuth as Huawei antenna, tilts to be as per design
Sector to be unlocked and brought on air
1st CS and PS call by NI team
Huawei
Nokia
Nokia
Nokia
Nokia
Taworn
Taworn
Amit
Taworn
Site Verification
DT team to conduct site verification tests once site is up and alarm free
DT logs to be provided to Nokia for analysis and SSV template completion
Results/Report of SSV to be shared with NetOne {DM}
Nokia
Nokia
Nokia
Nokia
Sharif
Sharif
Sharif
Site monitoring
Daily report
Nokia
Nokia
Derrick
Nokia
Nokia
Derrick
Da
TASKS
Site Installtion
XML Creation
OSS KPI for GSM creation in NetAct
SWAP sites by NI
SSV Complete
Weekly OSS KPI submission
Cluster Drive Test Complete
Site Acceptance
Cluster Acceptance
Start Date
11/1/2014
12/1/2014
1/15/2015
2/2/2015
2/3/2015
2/7/2015
3/2/2015
3/3/2015
3/15/2015
Duration
70
45
15
28
35
60
15
30
30
Site Installtio
XML Creat
SWAP sites by
SSV Comple
Site Acceptan
Cluster Acceptan
Days
Complete
Incomplete
70
45
12
0
0
0
0
0
0
Site Installtion
XML Creation
0
0
3
28
35
60
15
30
30
Incomplete
Complete
Start Date