The letter responds to a request from Dongfang Electric Corporation Ltd. to conduct an initial operation test of a gas turbine generator without having fully commissioned the site's firefighting system. The author expresses concern that conducting the test without proper fire protections in place would invite safety and insurance risks in the event of a fire during testing. The letter notes that Dongfang would be responsible for any losses from a fire if the protections are not complete when performance testing begins.
Original Description:
Original Title
M6-INITIAL OPERATION AND PERFORMANCE TEST OF GTG#1.doc
The letter responds to a request from Dongfang Electric Corporation Ltd. to conduct an initial operation test of a gas turbine generator without having fully commissioned the site's firefighting system. The author expresses concern that conducting the test without proper fire protections in place would invite safety and insurance risks in the event of a fire during testing. The letter notes that Dongfang would be responsible for any losses from a fire if the protections are not complete when performance testing begins.
The letter responds to a request from Dongfang Electric Corporation Ltd. to conduct an initial operation test of a gas turbine generator without having fully commissioned the site's firefighting system. The author expresses concern that conducting the test without proper fire protections in place would invite safety and insurance risks in the event of a fire during testing. The letter notes that Dongfang would be responsible for any losses from a fire if the protections are not complete when performance testing begins.
Deputy Project Manager & Site Manager Nandipur CCPP, Dongfang Electric Corporation Ltd. Site Office Nandipur, Distt: Gujranwala. SUBJECT:
425 MW COMBINED CYCLE POWER PLANT NANDIPUR
INITIAL OPERATION AND PERFORMANCE TEST OF GTG#1
References: DEC-S/NP-NESPAK/15-286 dated April 21, 2015
Dear Sir, This is in response to above referred letter. DECL has stated that any defect of firefighting system shall be separated with the successful continuous initial operation test of GT. In fact in our opinion it is a safety measure and its absence would have been invited risk of fire hazard leading to loss of property or human life. DECL through above referred letter intimated to carry out Performance test of GTG #1 without prior completion/commissioning of fire fighting system for main transformer. In this regard, it has to be noted that if the PT/RTR are carried out without proper fire fighting protection system DECL would be held responsible for any loss due to fire incident, as the insurance claims in such cases become invalid. Best regards, Very truly yours, for National Engineering Services Pakistan (Pvt.) Limited,