Base Uom Change
Language English
Header Data
Released On 11.02.1999
Release Status Released for Customer
Component
LO-MD-MM Material Master
Priority
Recommendations / Additional Info
Category
Consulting
Symptom
Within the material master record maintenance, you want to change the base unit of measure (base
unit). During the change, the system performs extensive checks in order to avoid inconsistencies in
the applications which use the material master.
In particular, the following checks are performed:
The base unit must not be defined as an alternative unit of measure for the material
Stock must neither exist for the previous period nor for the current period
No reservations or dependent requirements must exist for which the deletion indicator is not
set
No planned orders must exist
No purchase requisitions, purchase orders or scheduling agreements must exist for which the
deletion indicator is not set
No standard cost estimate must exist for the current or future period
If the base unit has dimensions, no serial number profile must be assigned
No sales and distribution documents must exist which have status Not processed or Partially
processed.
Other Terms
MARA-MEINS, MARA_MEINS, M3189
If necessary, all reasons mentioned above must be eliminated by archiving the objects listed.
Validity
Software Component From Rel.
SAP_APPL
22A
300
40A
45A
46A
46C
470
500
31I
40B
45B
46B
46C
470
500
References
This document refers to:
SAP Notes
724536 Changing the base unit of measure - program