MCV

Action Plan
Location:
Start Date:
Rev. Date:

MCV machining factory

Rev: 0

Manager:
Group:
Prepared by:

Eng. Emad

G
Y

Eng. Emad Karam

R
W
B

Green - Task Completed on Time


Yellow - Task May Be Late
Red - Task is Late
White - Task Re-Timed, No Status
Blue - Task Status is Incorrect / Not Updated
On Track (Bold Box/No Color)

Objective: Apply 5S in Tanks Station


ITEM

ACTION ITEM

ACTION LEADER

DATE
OPENED

TARGET
CLOSE
DATE

ACTUAL
CLOSE
DATE

STATUS HISTORY
LAST
UPDATE

Most Recent
Oldest

1 restudy work center capacity

a productivity for last six month as (actual produced hours /actual man hours ) i.e. output/input
b restudy the results with technology
2 schedule from SAP ( dispatching the universal planned orders and AS planned order
a maintain universal and AS routing ,mile stone , in house production
3 layout ( production line flow )
a issuing handling plan with schedule for interring and outing the tools and jigs
b restudy the production layouts
4 drawing the current value stream mapping
a determine lead time
b determine WIP
c solving the problems
d re drawing the new value mapping

05/19/2015

file:///var/www/apps/conversion/tmp/scratch_1/270702378.xls
Sheet1

MCV

Action Plan

Rev: 0

White - Task Re-Timed, No Status


Blue - Task Status is Incorrect / Not Updated