HANDOVER OF SCOPE OF WORK.

1. SEC CAMP OCCUPANY STATUS.


-REQUESTS FROM SEC FICHTNER NEED TO BE SIGNED BY SEC SITE MANAGER
OR PROJECT MANAGER.
2. DUTY ALLOCATION CAMP BOYS
-Goinda Bista supervisor of SEC camp and duty is divided as per list.
3. MAP OF THE CAMP
4. MAP OF OFFICE
5. IP TELEPHONE SYSTEM APPROVAL AND PURCHASE ORDER
-50% first payment has been done to Hamood and Hamid who is the supplier
for providing IP phone system installation and configuration. Work will be
started with in November as system equipments is awaited from CISCO for
the delivery.
6. SEC CAMP INTERNET NETWORKING APPROVAL AND PURCHASE ORDER
COMPLETED.
Bandwidth upgrade request is pending .Waiting for the quotation from
Sabhakah Net (ISP).
7. SUMMARY OF SEC IT EQUIPMENTS AND SOFTWARES
HHI IT engineer has the complete details regarding this.
8. SEC CAMP ACCOMONDATION REQUEST FORM
Form is used for new comers in SEC camp must be signed by Mr. Fahad or Mr.
Zamal or Mr. Hamdan.
9. SEC CAMP AND OFFICE MAINTAINEANCE REQUEST FORM
Any Maintenance problem in SEC camp and office is requested from
occupants.
10.IDEAL CATERING APPROVAL OF 95 SAR.
Preparing Monthly Catering Summary.
11.A-TYPE FUNISHING STATUS
12.D-TYPE FURNISHING STATUS
13.HEAD OFFICE APPROVAL FOR SEC FURNITURES
14.TV SYSTEM APPROVAL AND CONTRACT
Azmi Electronics-Any TV service problem is arise need to Call Mahin0503011362 available (7 am~7 pm)