ENGINEERING & PROJECT MANAGEMENT

SITE PROJECTS DEPARTMENT

REQUEST FOR INSPECTION


Project Title :

UPGRADATION OF POWER STACK FAN IN DR MODULE A & B

Project No. :

AF1221089

Project Type :

Affiliate :

0531841298

Contractor Contact Person

NORMAN MORALES

Tel:

Inspection Date

16/02/15

Time:

Place of Inspection

SSRS No.:

Discipline:

CIVIL

1400HRS

Rev. :

00

RFI No

M-036

CAMERON FAB
SHOP

Network No:
MECH.

ELECT.

INSTR.

S No.
6.2.3

Item to be Inspected
FINAL DIMENSIONAL INSPECTION OF
STC1,RD1&STC2 STACK B

Quantity
SEE
ATTACHED
DIMENSION
AL
REPORTS

Drawings No. / Remarks


4509-S00160-F6-001
REV.B
4509-S00160-F6-002
REV.B

4509-S00160-F6-003
REV.A
4509-S00160-F6-004
REV.C

4509-S00160-F6-009
REV.A
4509-S00160-F6-010
REV.A
4509-S00160-F6-007
REV.B
4509-S00160-F6-008
REB.A

Satisfactory
Results
Unsatisfactory
Comments

QA/QC Engineer /
Inspector Name

Signature

Date

Construction Supervisor /
Project Engineer

Signature

Date

EPM-SPD-PC-F-008 Rev. No.: 00


Ref Doc.: EPM-SPD-PC-P-004

Page 1 of 2

ENGINEERING & PROJECT MANAGEMENT


SITE PROJECTS DEPARTMENT

REQUEST FOR INSPECTION


Project Title :

UPGRADATION OF POWER STACK FAN IN DR MODULE A & B

Project No. :

AF1221089

Contractor

EPM-SPD-PC-F-008 Rev. No.: 00


Ref Doc.: EPM-SPD-PC-P-004

Project Type :

NORMAN MORALES

Affiliate :

Signature

Rev. :

HADEED

Date

00

Page 2 of 2