Professional Documents
Culture Documents
Project Management and Scheduling: Objectives of Project Scheduling Network Analysis Scheduling Techniques
Project Management and Scheduling: Objectives of Project Scheduling Network Analysis Scheduling Techniques
Network control
Track the progress of a project on the basis
of the network schedule and taking
corrective actions when necessary.
Evaluate the actual performance against
expected performance.
PERT/CPM
Node
4
Merge point Successor
Burst point
2
Arrow
Predecessor
Critical path
Earliest starting time
ES
Earliest completion time EC
Latest starting time LS
Latest completion time LC
Activity Capital letter
Duration
t
Example
Activity
A
B
C
D
E
F
G
Predecessor
A
C
A
B, D, E
Duration
2
6
4
3
5
4
2
A
2
End
D
3
G
2
B
6
S ta rt
C
4
E
5
0
A
2
0
2
D
3
0
0
S ta rt
0
C
4
B
6
4
F
4
E
5
11
G
2
11
End
11
0
4
0
A
2
0
3
B
6
0
0
C
0 4
6
9
11
11
D
3
F
4
0
S ta rt
9
9
E
5
9
9
G
2
11
11
11
End
11
11
A
2
0
3
B
6
0
0
0
C
4
0
D
3
11
11
5
9
F
4
S ta rt
0
9
9
E
5
0
9
9
G
2
0
11
11
11
End
0
11
11
Critical path
F
4
A
2
End
D
3
B
6
S ta rt
C
4
G
2
E
5
Computational analysis
of network
Forward pass: each activity begins at its
earliest time. An activity can begin as soon
as the last of its predecessors is finished.
Backward pass: begins at its latest
completion time and ends at the latest
starting time of the first activity in the
project network.
PERT
PERT is an extension of CPM.
In reality, activities are usually subjected to
uncertainty which determine the actual
durations of the activities.
It incorporates variabilities in activity
duration into project entwork analysis.
The poetntial uncertainties in activity are
accounted for by using three time estimates
for each activity
Average
Task A
2
4
6
4
Task B
3
4
5
4
2
(b-a)
s2 = 36
PERT
Calculate the expected time for each
activity
Calculate the variance of the duration of
each activity
Follow the same procedure as CPM does to
calculate the project duration, Te
Calculate the variance of the project
duration by summing up the variances of
the activities on the critical path.
A PERT Example
Activity Predecessor
te
s2
1
5
2
1
4
3
1
2
6
4
3
5
4
2
4
7
5
4
7
5
3
2.17
6.00
3.83
2.83
5.17
4.00
2.00
0.2500
0.1111
0.2500
0.2500
0.2500
0.1111
0.1111
A
B
C
D
E
F
G
A
C
A
B, D, E
) = P(z<= -1.2793)
) = P(z<= 2.5585)
Gantt Chart
Gantt chart is a matrix of rows and
columns. The time scale is indicated along
the horizontal axis. Activities are arranged
along the vertical axis.
Gantt charts are usually used to represent
the project schedule. Gantt charts should be
updated periodically.
Gantt Chart
G
F
E
D
C
B
A
1
10
11
Linked Bars
Progress - monitoring
Milestone
Task - combinations
Phase-Based
Multiple-Projects
Project-Slippage-tracking
10
11