31st May 2013

Projct Manager,
Qserve ( Pvt. ) Ltd.,
No. 31B, Albert Place,
Dehiwala.
Dear Sir,
PROPOSED BUILDING OF MOVENPICK CITY HOTEL AT DHARMAPALA MAWARHA
COLOMBO 03 FOR SOFTLOGIC CITY HOTELS ( PVT ) LTD.

We are pleased to submit our quotation for above work.


Cost for additional concrete filling in skin wall = Rs.
The above prices does not include VAT.
Additional time duration for above work - minimum 10 days

We hope that our quotation will meet your requirements and waiting for your kind approval.

Thanking you,
Yours faithfully

C C Mr. Stepahn Anthonisz ( CEO ) - Softlogic City Hotels ( Pvt. ) Ltd.

Prof. Chitra Weddikkara ( E.P.M.) - Qserve (Pvt) Ltd.

PROPOSED MOVENPICK CITY HOTEL PROJECT

SUMMARY
ITEM NO

A
i

DESCRIPTION

ADDITION
Additional concrete filling , formwork & reinforcement for
basement second floor area.
Total Cost of Addition

OMMISSION
Reduced slab area at basement second floor.

i
iii

Concrete Work
Reinforcement Work
Total Cost of Ommission

Total cost for additional

( item 'A' - 'B' )

( =10,369,924.26 - 1,449,367.20)

Note :

01. All above rates are exclusive of VAT.

RATE (Rs.)

0.00

0.00

0.00

PROPOSED MOVENPICK CITY HOTEL PROJECT

V.06 ADDITIONAL COST FOR PILE CAP INSTEAD OF CAPPING BEAM IN GROUND FLOO
ALONG GRID 'L' )
Item
No.

Description

Addition and ommission of front pile cap (Along


Grid 'L' )

Additional concrete for pile cap

Unit

Qty.

m3

56.93

m2

38.95

18.04

Rate: BOQ / Concrete / item no F.04


ii

Additional form work for pile cap


Rate: BOQ / Formwork / item no F.151

iii

Additional reinforcement for pile cap


Rate: BOQ / Reinforcement / item no F.309
Additional cost for pile cape instead of capping
beam in ground floor front side

Note : 01. All above rates are exclusive of VAT.

EAM IN GROUND FLOOR FRONT SIDE. (

Rate ( Rs. )

17,081.00

Amount (Rs.)

972,421.33
0.00
0.00

1,337.00

52,076.15
0.00
0.00

174,640.00

3,150,505.60
0.00

4,175,003.08

REINFORCEMENT QUANTITY OF CAPPING BE


( ACCORDING TO TENDER DRAWINGS )

PING BEAM

NGS )

REINFORCEMENT QUANTITY OF CAPPING BE


( ACCORDING TO NEW DRAWINGS )

PING BEAM

GS )

OMMISSION