Professional Documents
Culture Documents
PERT/CPM Construction
PERT/CPM Construction
CONSTRUCTION
PRECEDES
DUR
D,F
END
END
END
END
ACT
PRECEDES
DUR
D,F
END
END
END
END
B
2
3
1
A
2
D
6
K
4
E
7
F
3
H
2
END
5
O
C
5
M
1
10
N
6
11
ACT
PRECEDES
DUR
D,F
END
END
END
END
B
2
0
A
D
6
3
E
7
15
K
4
H
2
11
17
F
3
10
20
O
C
5
M
1
10
N
6
12
END
11
ACT
PRECEDES
DUR
D,F
END
END
END
END
B
2
11
13 J
11
9
0
8
3
D
6
12
F
3
3
E
7
15
16
K
4
18
H
2
20
20
15
20
20
O
C
5
M
1
10
N
6
12
END
12
11
ACT
PRECEDES
DUR
D,F
END
END
I, E
J, H
END
M, G
END
B
2
3
1
A
2
D
6
K
4
E
7
F
3
H
2
END
5
O
C
5
M
1
10
N
6
11
ACT
PRECEDES
DUR
D,F
END
END
I, E
J, H
END
M, G
END
B
2
I
2
F
3
8
K
J
3
E
7
15
H
2
6
5
M
1
17
20
10
N
6
12
END
10
5
C
11
11
ACT
PRECEDES
DUR
D,F
END
END
I, E
J, H
END
M, G
END
B
2
11
I
2
18
11
3 2
D
5
2
12
F
3
J
3
16
13
11
6
5
E
7
15
18
H
2
15
5
M
1
11
17
15
20
10
N
6
12
END
10
5
C
11
12
ACT
PRECEDES
DUR
D,F
END
END
I, E
J, H
END
M, G
END
B
2
11
I
2
3
0
18
11
A
2
D
5
2
12
F
3
J
3
16
13
11
6
5
E
7
15
18
H
2
15
5
M
1
11
17
15
20
10
N
6
12
END
10
5
C
11
12
Definition of Terms
Critical Path the longest route in the network of activities representing the project
- duration of CP = duration of the project
- there maybe more than one CP in a project and may shift as the project
moves towards completion
Forward Pass
Earliest Start Time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors
EF= ES + t
Backward Pass
ACT
ES
EF
8
15
15
17
10
4
2
7
DM1
2
4
DM2
11
5
DM3
0
5
12
12
20
I
2
F
3
8
K
J
3
E
7
15
H
2
6
5
M
1
17
20
10
N
6
12
END
10
5
C
11
11
ACT
LF
LS
11
18
11
20
18
15
12
20
15
11
13
B
2
DM1
11
11
16
13
DM2
18
18
20
16
DM3
15
15
6
12
20
12
I
2
13
18
11
9
11
11
3
0
A
2
2
12
F
3
11
J
3
16
E
7
18
H
2
15
END
20
O
C
5
15
5
M
1
10
N
6
11
12
ACT
ES
EF
LF
LS
Float
TF
11
15
18
11
15
17
20
18
15
12
10
10
20
15
10
11
13
11
DM1
11
11
16
13
DM2
18
18
11
20
16
DM3
15
15
12
12
12
20
20
12
9
9
14
10
0
0
0
TF = LS - ES
ACT
PRECEDES
DUR
C, D, F
F, D
E, G, I
E, G, I
10
G, I
END
END
A
4
ACT
PRECEDES
DUR
C, D, F
D, F
E, G, I
E, G, I
10
G, I
END
END
C
5
E
2
H
8
START
J 0
B
7
D 10
F
6
K 0
G 4
I
9
END
START
PRECEDES
DUR
C, D, F
D, F
E, G, I
E, G, I
10
G, I
END
END
A
4
ACT
C
5
E
2
4
17
J 0
K 0
17
F
6
13
29
G 4
4
B
7
H
8
6
21
D 10
19
26
I
9
END
0
START
ACT
PRECEDES
DUR
C, D, F
D, F
E, G, I
E, G, I
10
G, I
END
END
A
4
12
C
5
J 0
0
D 10
4
B
7
17
17
19
11
13
H
8
29
29
17
20
29
G 4
17
F
6
6
21
K 0
E
2
21
19
I
9
END
26
START
PRECEDES
DUR
C, D, F
D, F
E, G, I
E, G, I
10
G, I
END
END
A
4
ACT
12
C
5
J 0
0
D 10
4
B
7
17
17
19
11
F
6
K 0
13
H
8
29
21
26
17
20
29
G 4
17
E
2
21
19
I
9
END
Obtain an estimate of regular and crash time plus the cost of each activity.
Determine the length of all path and their float time.
Determine which activities are on the critical path.
Crash the critical activities in the order of increasing costs as long as crashing
cost do not exceeds the benefits.
From the following data, develop an optimum time cost plan assuming that
total crashing cost is P15, 000.
Act
Normal
Time
Crash
Time
12
10
P6,000
2,000
6,000
4,500
7,000
A
8
Cost/day
to Crash
B
12
5
C
7
D
6
F
4
E
9
A-B-F = 24days
C-D-E-F = 26days Critical Path
Rank the Critical Path activities in order of lowest crashing cost.
Act
Normal
Time
Crash
Time
Available
Days
Cost/day to
Crash
2,000
4,500
6,000
7,000
A
8
B
12
5
C
7
D
6
E
9
F
4
Shorten the project one day and then check after each reduction to see which path is critical
Critical Path
A
8
B
12
5
C
7
D
6
E
9
F
4
Path
Activity
Crash Cost/day
No more Reduction
6,000
Act
Normal
Time
Crash
Time
Available
Days
Cost/day
to Crash
2,000
4,500
7,000
12
10
6,000
No More Reduction
6,000
7,000
6,000
4,500
7,000
A-B-F = 24days
C-D-E-F = 24days
A-B-F
C-D-E-F
A
8
Critical Path
B
12
5
C
6
D
6
E
8
F
4