This document is a pre-functional checklist for the HVAC upgrade project at the Volk Gym building at Colorado School of Mines. It lists 18 items that are to be verified, including confirming that the main transformer has weatherproof enclosure and tamper resistant construction, the transformer is properly labeled and installed, the grounding system meets specifications, spare fuses were provided, and the electrical meter and current transformers were correctly installed.
This document is a pre-functional checklist for the HVAC upgrade project at the Volk Gym building at Colorado School of Mines. It lists 18 items that are to be verified, including confirming that the main transformer has weatherproof enclosure and tamper resistant construction, the transformer is properly labeled and installed, the grounding system meets specifications, spare fuses were provided, and the electrical meter and current transformers were correctly installed.
This document is a pre-functional checklist for the HVAC upgrade project at the Volk Gym building at Colorado School of Mines. It lists 18 items that are to be verified, including confirming that the main transformer has weatherproof enclosure and tamper resistant construction, the transformer is properly labeled and installed, the grounding system meets specifications, spare fuses were provided, and the electrical meter and current transformers were correctly installed.
PROJECT: Volk Gym HVAC Upgrade EQUIPMENT: Building Distribution System
PROJECT #: M627-Phase 3 CSM Plant Facilities shall authorize any duplication of this form. CSM COMMENTS Comp. Appr # ITEM Date oval Date
1 Main transformer has weather proof enclosure and
tamper-resistant construction.
2 Building main transformer size & voltage is
according to the specifications. 3 The transformer is deadfront construction. 4 Transformer is installed level. 5 Transformer accessories meet project specifications. 6 Transformer enclosure color meets campus standard. 7 Transformer is labeled properly. Grounding system is installed as called in 8 specification & on the drawings. Contractor delivered spare fuses to CSM Electric 9 Shop as per specifications. Transformer hinged access doors are lockable with 10 CSM standard padlock. Transformer has 15 KVA, 200 AMP loadbreak & 11 built-in stress cones. There are solid state adjustable trip circuit breaker in 12 the secondary component as shown on the drawings and described in specifications. Breakers are rated as per specifications and provided 13 with ground fault shunt trip sensor when exceeding 600 volts phase for each service disconnecting means rated 1,000 AMP or more.
14 All one line diagram and electrical lay-out plan as
built are delivered.
15 Meter is installed properly Lanois & GYR
#60541100400 with base. CT’s are sized and installed correctly usually 60% of 16 max load. Separate Conduit is installed for Staefa interface 17 with building Electrical metering device.
18 CT’s ratios are defined by the project electrical
engineer and meter is programmed correctly. Prepared by: Hooshang Salehizadeh