King Abdullah Financial District Project Work Progress Status As of 2-June-2012 DB06C-EL-SEIF (Parcels 3.04, 3.05)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

KING ABDULLAH FINANCIAL DISTRICT PROJECT

WORK PROGRESS STATUS AS OF 2-JUNE-2012


DB06C-EL-SEIF (Parcels 3.04, 3.05)

Parcel 3.04

Planned
Finish

1-Nov-08
22-Nov-10
7-May-11

Forecast
Finish

Planned
% Complete

Current
% Complete

Structure (Concrete)

COMPLETED

Blockworks

COMPLETED

Variance (%)

Plastering Works/ Walls Dry Lining Work

1-Feb-11

100.00%

96.00%

4.00%

Faade Works

8-Jan-11

100.00%

99.00%

1.00%

Wall Finishes:1st paint, Marble, Ceramic &


Granite

22-Jan-11

100.00%

85.00%

15.00%

Floor Finishes (Marble, Ceramic & Granite)

12-Jan-11

100.00%

83.00%

17.00%

Elevator

27-Feb-11

100.00%

90.00%

10.00%

Plumbing

24-Jan-11

100.00%

87.00%

13.00%

HVAC

15-Jan-11

100.00%

90.00%

10.00%

Fire Fighting

17-Jan-11

100.00%

91.00%

9.00%

Electrical

3-Jan-11

100.00%

86.50%

13.50%

Parcel 3.05

Planned
Finish

Planned
% Complete

Current
% Complete

Variance (%)

Forecast
Finish

Structure (Concrete)

COMPLETED

Blockworks

COMPLETED

Plastering Works/ Walls Dry Lining Work

3-Nov-10

100.00%

98.00%

2.00%

Faade Works

9-Dec-10

100.00%

99.00%

1.00%

Wall Finishes:1st paint, Marble, Ceramic &


Granite

30-Dec-10

100.00%

95.00%

5.00%

Floor Finishes (Marble, Ceramic & Granite)

13-Dec-10

100.00%

94.00%

6.00%

Elevator

28-Jan-11

100.00%

90.00%

10.00%

751
166
Slab Level
(FL)

Slab Level
(FL)

Plumbing

25-Dec-10

100.00%

95.00%

5.00%

HVAC

16-Dec-10

100.00%

96.00%

4.00%

Fire Fighting

18-Dec-10

100.00%

95.00%

5.00%

Electrical

4-Dec-11

100.00%

92.50%

7.50%

Preliminary Design
Planned
Finish

3.04
3.05

Forecast
Finish

Detailed Design
Planned
Finish

Forecast
Finish

Final Design
Planned
Finish

As reported by ESEC, Final design has been completed

Forecast
Finish

Original Contract Duration:


81.89749 Spent Duration:
18.10251 Remaining Duration:

911 Days
911 Days
0 Days

100%
0%

OVERALL
Core Level
(FL)

Core Level
(FL)

Planned
Finish

Forecast
Finish

Planned
% Complete

Current
% Complete

Variance
(%)

Earned Value
%

7-May-11

18-Sep-12

100.00%

90.00%

10.00%

82.47%

Planned
Finish

Forecast
Finish

Planned
% Complete

Current
% Complete

Variance
(%)

Earned Value
%

7-May-11

18-Sep-12

100.00%

93.50%

6.50%

86.25%

REMARKS

REMARKS

7-May-11

18-Sep-12

Manpower
Indirect

Direct

770

626

100.00%

93.50%

6.50%

86.25%

HSE (Site Accident Report) Cumulative


FAC

Recordable

Fatal

NM

Fire incidents