Cary Woods Elementary School

715 Sanders Street, Auburn, Al 36830


Resource List, Quantity Take-Off & Cost Estimate, Recommended Concrete Design
Resource List:

Tools & Equipment: Broom ( for finish), floats, joint tools, screeds, flat shovels, wheel
barrow, sledge hammer, hose pipe (250)
Materials: Concrete, grade stakes, clear plastic, 1x4 form boards, caution tape
Labor: 20 man hours
Quantity Take-Off
6.5 CY of conventional concrete
1 Sand Base
120- 2 x 2 x 24 grade stakes
3mil plastic sheathing
22- 1x4x12 spruce form boards
Yellow Caution Tape
Cost Estimate

6.5 CY of conventional concrete = $650


120- 2 x 2 x 24 grade stakes= $8.98 per 25 bundle= $53.88
3mil clear plastic sheathing (100x12) = $33.97
22- 1x4x12 spruce form boards = $5.57ea= $122.54
Yellow Caution Tape (3x100) = $7.97
1 Sand Base, (1x4x120) =4,000#, or 1.5CY= $3.67/50# bag= $293.6
TOTAL = $ 1,161.96

Concrete Mix Design

4000 PSI, with a 4 Slump