DAILYREPORTFROM SITE

S.No:32

1.

Date 01.02.2013

Site: M/s Baldev alloys pvt. LTD.


Vwta020,VWHA052,053,054

Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)

Nil.

2.

Details of communications sent to HO


on

Daily report ,guest house asset detail, C- form

3.

Details of consignments / materials


received from HO / others

Nil.

4.

Details of payments received from HO /


others

Nil.

5.

Attendance with details


:

MR.M.E.MANIKANDAN(2141)

5.1

Staff (VEESONS)

Mr. DINESH KUMAR.S (1832)

5.2

6.

Contract Workers (Contractor wise)

Important brief feedback about Fabrication


/ Erection / Commissioning (delay with
reference to schedule, major problems
etc.,)

Utkal Engineers:
Boiler: Supervisor:00 IB
00; Riger-02;grinder-0 Helper-05(Total=09)

1.contractor man power shortage

2. Radiography film required from con


3.customer side insert plates

7.

Materials, documents, payments urgently


required from HO with details

1. Utkal engg Contractor payment.

8.

Any urgent / important site complaints

UTKAL Engineering Should be


increasing his manpower.
Refractory contractor required
for 3XWHRB boiler ABC Ducts.

Site status:

VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) Dividing chute Support erection work completed.
2) Air heater to esp ducting Support ground fit up Work
completed.
3) LP dosing piping erection work U/P.
4) Drum top level plat form hand rail work completed.
5) Integral piping supports erection work U/P.

ESP;
1) Sealing roof plates erection arrangement work U/P.

Prepared by (Name):

M.E.MANIKANDAN

Checked & Approved by (Name) :

M.E.MANIKANDAN

Signature:

Signature:

Staff No : 2141

Staff No. :2141