Dailyreportfrom Site: Date 11.02.2013
Dailyreportfrom Site: Date 11.02.2013
S.No:35
1.
Date 11.02.2013
Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)
Nil.
2.
Nil.
3.
Nil.
4.
Nil.
5.
MR.M.E.MANIKANDAN(2141)
5.1
Staff (VEESONS)
5.2
6.
Utkal Engineers:
Boiler: Supervisor:01 IB
03; Riger-03;grinder-0 Helper-05(Total=17)
7.
8.
Site status:
VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) PA Line Dummy Flange Fit Up work U/P.
2) PA line to Mixing Nozzle gasket fixing work U/P.
3) Feed water discharge header to WHRB I,II,III eco inlet piping
HP welding work U/P.
4) Air heater & pressure blower erection work U/P.
5) ID fan outlet to chimney ducting erection work U/P.
ESP;
1) Air heater & pressure blower erection work U/P.
2) Over roof railing erection work U/P.
Prepared by (Name):
M.E.MANIKANDAN
M.E.MANIKANDAN
Signature:
Signature:
Staff No : 2141