Professional Documents
Culture Documents
Manual Penyelian Tapak (Site Supervision Manual) : 6.1 Objectives
Manual Penyelian Tapak (Site Supervision Manual) : 6.1 Objectives
Manual Penyelian Tapak (Site Supervision Manual) : 6.1 Objectives
372
GOVERNMENT OF MALAYSIA
CONSULTANT
CONTRACTOR
373
The main role of the consultant engineer are mainly all site supervision
of construction and administration of the Contract with respect to :
a) supervision
b) testing
c) examination of materials and workmanship
d) measure of work carried out
In carrying out the work and to ensure the proper construction of the
works in accordance and in compliance with the requirements of the
Tender Document, construction drawings and the specification, the
Consulting Engineer (the Engineer) shall provide suitable qualified
supervisory and office administration staff.
374
6.32
375
for
work
measurement,
progress
payment
for
preparation
and
completion
of
final
adequate
site
documentation
of
work
377
10. To assist the CRE in the measurement of all works and keep all
necessary record.
11. To assist CRE in checking the Contractors interim valuation
and assist him in checking his final account.
12. To implement the QA/QC measure on site.
c. Inspector of Work
d. Clerk/Typist
Assisting the CRE in the following:
1. Office administrative work, preparation of monthly reports.
2. Typing miscellaneous correspondence, report, memo, minutes
of meeting and filing system.
378
379
380
381
383
I.
384
i.
ii. Top 300 mm of sub grade lower sub base: 1 test per 300
metre square for each layer of compacted material.
iii. Gravel surface sub base: 1 test per 200 metre square for
each layer of compacted material.
385
iv. Crushed aggregate road base: 1 test per 150 metre square
for each layer of compacted material.
v. Shoulders (earth/gravel): 1 test per 150 metre square for
each layer of compacted material.
vi. Granular bedding for culverts and pipes: 1 test per 25 metre
length of culvert pipe.
vii. Granular bedding for other structure: 1 metre per layer per
25m length of structure, or per footing, or per 200 metre
square of foundation slab.
viii. Backfill for structure: 2 test per layer per structure for each
25m length of structure.
ix. Backfill for subsoil drain: 1 test per layer per 50 metre length
of trench.
6.62 Earthwork and Flexible Pavement Materials
i.
Determine
Atterberg
limits,
swelling
or
shrinkage
ii.
386
a.
b.
Gradation analysis
c.
d.
e.
f.
ii.
iii.
iv.
388
c. Concrete
1 batch of each concrete class or type shall be sample. Each
sample are tested for workability by slump test, 3 standard
comprehensive strength test cube and 1 for testing at 7 days and 2
for testing at 28 days.
Slump tests shall be carried out regularly during the production of
concrete.
d. Pre-cast Concrete Culvert Pipes
RCP sections that are cast on site are subject to inspection and
testing of materials and workmanship. Samples are to be loaded to
determine 28 days strength after casting, as well as to test for
compliance with load bearing specifications.
Sampling at 5% of pipe sections of each class of size of pipe
fabricated are to be tested at cracking loads, while at least 2% of
RCP pipe sections shall be load tested to failure, i.e. ultimate
strength test.
Load tests are to be carried out at the site or at concrete product
factory with the suitable test equipment to facilitate testing.
389
a.
b.
c.
d.
e.
setting or curing
f.
g.
h.
i.
j.
pressure test
k.
leakage test
Switchboard
390
water stop
j.
guardrails
k. gabions cages
l.
paints
m. geotextile
n. fabrics filter materials
o. thermoplastic materials for road markings
p. joint fillers
q. waterproofing and damp-proof materials
r. bricks, etc.
391
Fax :
03-8367254
392
If you discover that the materials do not comply with the Specifications,
request the laboratory staff to check them and make sure that your
Engineer is informed is informed of the test results.
6.92 ADMINISTRATION
a. General
i. Hours of work will generally be defined by the Engineer under
whom you are working. Your particular duties will be
allocated by the Engineer.
ii. Time sheets must be filled in at the appropriate time and
signed by the Engineer
b. Personal Diaries
These are to be completed daily by all staff to record events
pertaining to the progress of the Works and in particular with
regard to their own involvement in these events, whether by
observation or direct action. Items to be recorded shall include :
i.
ii.
iii.
iv.
v.
local
authorities
and
public
utility
representatives.
394
vi.
vii.
viii.
c. Daily Reports
395
vi.
vii.
ix.
Laying sub-base
x.
ii.
plant
and
outputs,
weather,
material
reference
to
moisture
contents,
also
396
iv.
v.
vi.
vii.
of
labour,
plant
and
constructions,
reinforcement, etc.
viii.
ix.
x.
397
6.93 GENERAL
A. Setting Out
i. The responsibility for setting out the Works is the Contractors.
The Engineer with the assistance of the Inspector of Works
will check that the Contractors setting out is correct.
ii. Before the Contractor starts any aspect of the Works, make
sure that the Engineer is notified. To assist with the detailed
setting out, reference stations will be established. Check these
occasionally to see that they have not been damaged. If there
is suspected damage, notify the Contractor immediately as
well as the Engineer.
iii. Always check that you and the Contractor are working to the
latest edition of the Drawings. A register of Drawings is kept
by the Site Clerk or another in the Engineers site office.
iv. Where simple checks from the reference points can be done,
these shall be carried out by the Engineer, Inspectors of
Works and technicians.
398
i.
The job can only be as good as the materials that are used.
Substandard materials will give a substandard job. The
responsibility for testing for acceptance is generally that of the
Engineer (soil and materials). You should see that materials that
have deteriorated are not used e.g. concrete that has been
mixed too long or rebar that has mill scale or excessive rust.
ii. Report to the Engineer any new material that the Contractor
brings to Site including a change in fill material in the
earthworks.
The end product of the job will depend very largely on the
performance of the Constructional Plant and labour. Check
particularly that vibrating equipment, rollers, concrete vibrators,
etc. are functioning correctly. If not, advise the Contractor and
inform your Chief Resident Engineer.
399
ii.
ii.
400
ii.
iii.
ii.
Check all diversion and plant crossings to see that they are
clean and do not have potholes.
plant
crossing,
check
that
the
Contractors
safety
H. Measurement Records
i.
ii.
iii.
ii.
iii.
iv.
always be given to the Contractor. The reason for this is that the
Contract is between Employer and the Contractor.
K. Progress
Draw to the attention of your Engineer any aspect of the work that
seems to be slow so that he may take it up at a higher lever. Try to
find out the reasons at your level.
Weak scaffolding.
403
6.10 MAINTENANCE
i.
ii.
This may not mean that all works are fully complete, but are in a
state of practical completion to enable the owner to occupy and
use the same.
iii.
iv.
404
6.11 CAUTION
i.
ii.
405