Professional Documents
Culture Documents
Completion Certificate
Completion Certificate
Date: 30 june,2015
This is certify that work releted to Provision of Decommissiong Ex-used Sebsea Pipeline at Crossing #2 of Alur
Pelayaran Barat Surabaya has been completed on 30th June,2015 by the construction by the construction BC
Pioner 88, details of which are as below:
1.
PROJECT
: PROVISION OF DECOMMISIONING EX-USED SUBSEA
PIPELINE AT CROSSING #2 OF ALUR PELAYARAN BARAT SURABAYA
2.
COMPANY
3.
CONTRACTOR
4.
CONTRACT NO.
: SS1/PRJ-037/15/APR
5.
: 16 JUNE 2015
6.
: 30 JUNE 2015
7.
PIPELINE LENGTH
: 3.2 KM
8.
PIPELINE ID
: 16 INCH