Assignment Wbs - Question
Assignment Wbs - Question
You have been assigned as the planner for Company XYZ. Your company had won a 14 Million Ringgit project from Developer ABC for
Construction and Completion of 56 Units Double-Storey Terrace Houses at Bandar Indah Setia.
Create the WBS elements either by graphical method, or outline method to lists the activities involve in the construction of the housing
project. Details of the Project were as follows;
TNB
Substation
wakaf
Guard
house
grass
trees
BLO
CK
D- 7
UNI
TS
grass
BLO
CK
C-7
UNI
TS
grass
PLAYGROUND
BLOCK B- 7 UNITS
BLOCK E- 7 UNITS
BLOCK G- 7 UNITS
BLOCK F- 7 UNITS
BLOCK H- 7 UNITS
walkway
EMS.FKAAS
BLOCK A- 7 UNITS
Road
Item
House
Description
Ground Floor Finishes Living
- Dining
- Kitchen
TNB
substation
- bathroom 2
- guest room
- Master bedroom
- Master Bathroom
- Bedroom 1
- Bedroom 2
- Bathroom 1
- Family area
- Staircase
- Roofing
- External Finishes
-Building
Guard House
- External
- Building
Landscape
- hard Landscape
Infrastructure
EMS.FKAAS
- Soft landscape
- Road
- Water Reticulation
- Street Lighting
- Electrical Supply
- Drainage and Sewerage System
EMS.FKAAS