CONSTRUCTION PLANNING AND SCHEDULLING

You have been assigned as the planner for Company XYZ. Your company had won a 14 Million Ringgit project from Developer ABC for
Construction and Completion of 56 Units Double-Storey Terrace Houses at Bandar Indah Setia.
Create the WBS elements either by graphical method, or outline method to lists the activities involve in the construction of the housing
project. Details of the Project were as follows;

TNB
Substation

wakaf

Guard
house

grass

trees

BLO
CK
D- 7
UNI
TS
grass

BLO
CK
C-7
UNI
TS

grass

PLAYGROUND

BLOCK B- 7 UNITS

BLOCK E- 7 UNITS

BLOCK G- 7 UNITS

BLOCK F- 7 UNITS

BLOCK H- 7 UNITS

walkway

EMS.FKAAS

BLOCK A- 7 UNITS

Road

CHAPTER 2. WORK BREAKDOWN STRUCTURE

CONSTRUCTION PLANNING AND SCHEDULLING

Item
House

Description
Ground Floor Finishes Living
- Dining
- Kitchen

1st Floor Finishes

TNB
substation

- bathroom 2
- guest room
- Master bedroom
- Master Bathroom
- Bedroom 1
- Bedroom 2
- Bathroom 1
- Family area
- Staircase
- Roofing
- External Finishes
-Building

Guard House

- External
- Building

Landscape

- hard Landscape

Infrastructure

EMS.FKAAS

- Soft landscape
- Road
- Water Reticulation
- Street Lighting
- Electrical Supply
- Drainage and Sewerage System

Floor tiling, wall plastering & painting, ceiling-plasterboard


Floor tiling, wall plastering and painting, ceiling-plasterboard
Floor tiling, wall tiling at 5 height from floor finishes, plastering
and painting 3 above wall tile, ceiling skim coat
Floor tiling, wall tiling, ceiling board
Floor tiling, wall plastering & painting, ceiling plaster board
Timber Flooring , wall plastering & painting, ceiling plaster board
Floor tiling, wall tiling, ceiling board
Timber Flooring , wall plastering & painting, ceiling plaster board
Timber Flooring , wall plastering & painting, ceiling plaster board
Floor tiling, wall tiling, ceiling board
Timber Flooring , wall plastering & painting, ceiling plaster board
Timber finishes with GI hand railing
Roof Tile
Front and Rear Gate, porch with pebblewash and cement screed
finishes, concealed drain.
Cement screed Floor finishes, wall with plastering and painting,
roof tile
Brickwall Fencing, Premix
Floor Tiling, wall plastering and painting for internal and external,
toilet finishes (wall and floor Tile), Ceiling Board, Roof Tile
Walkway using Interlocking bricks
Children Playground with rubber floor, Slides, swing etc.
Wakaf
Trees, grass
Standard premix

CHAPTER 2. WORK BREAKDOWN STRUCTURE

CONSTRUCTION PLANNING AND SCHEDULLING

EMS.FKAAS

CHAPTER 2. WORK BREAKDOWN STRUCTURE