The Gantt Chart in

Project
Management

What is a Gantt
Chart?
A type of chart that shows the
Work
Breakdown Structure (WBS) in
terms of the start
and finish dates of its components,
activities and
sub-activities.

Brief history of the Gantt


Chart
developed by Henry Gantt
first major use was during the First
World War
started as a simple scheduling tool
today has many more complex but
powerful
versions (ex. Gantt Excel, MS
Project)

MS Project
http://www.ese.upenn.edu/seniordesign/resources/MS_Project_Tutorial.pdf

Show Gantt Excel

Why Use Gantt


Chart?
Can show the relationships
between
components and activities
which activities to do first so
that the
next can be started
which activities can be done
at the
same time

Uses of the Gantt


Chart?
Can show current schedule status
(what has been completed as of
today)
Can be used to plan strategies to
meet expected outputs

How to prepare a Gantt


Chart?
1. Refer back to the WBS in outline
form.
2. Add columns to contain the time
elements (ex,
days, weeks, months, years)
3. Mark the time schedule when you
plan to begin
and end an activity

How to prepare a Gantt


Chart?
Tip:
Imagine that you are already
implementing your project. What
specific activities will you do when?