Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 15

277981273.

xlsx

OPERATIONS REPORT OF BALNAVES PROJECT - MOBILIZAT


V1.0

Prepared By :

1. General Project Information


Project Ref. No.
Project Name
Project Report Date
Cargo Weight
Project Owner
Client
Project PIC

:
:
:
:
:
:
:

Equipment/s

06-11-Asiaflex-TSS-EN
BALNAVES PROJECT - MOBILIZATION
###
100
mTon
(Approx.)
Asiaflex Product S/B
Asiaflex Product S/B
Mr. Aman
24
2

x
x

axlelines Bogie
units
Power Pack

Scheuerle SPMT

Project & Engineering : Amarudin & Edmund


: Fauzi, Jafree, Hafizi, Anuar & Prawit
Operations

Shifting (Work Platform)


Time
Planning Start Date
Planning Finish Date

:
:

Variance

11/5/2013 9:30
Actual Start Date
11/5/2013 10:30 Actual Finish Date
60
2:00
h:mm
=

:
:
200.00 %

Shifting (TSS)

Time
Planning Start Date
Planning Finish Date

:
:

Variance

General Commets

: 1) A busy schedule of using Manitowoc crane has caused delays for th


shifting. The crane is involed in internal lifting during our operation.
2) Bogie arrived late caused part of the reason of delays.

11/5/2013 13:00 Actual Start Date


11/5/2013 14:00 Actual Finish Date
60
0:40
h:mm
=

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

:
:
66.67 %

277981273.xlsx

OPERATIONS
REPORT OF BALNAVES PROJECT - MOBILIZAT
1) A busy schedule of using Manitowoc crane has caused delays for th
shifting. The crane is involed in internal lifting during our operation.
2) Bogie arrived late caused part of thePrepared
reason ofBy
delays.
:

V1.0

2. Activities Records
11/4/2013
1600
1645
1730

: Unloading of bogie & accessories


: Bogies assembling & set up
: Activities end for the day

11/5/2013
0820
0850
0910 - 0955
1025
1035
1040
1054
1110
1200 - 1300
1320
1340 - 1410
1420
1425
1432
1449
1508
1605
1700

:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:

Operation crew onsite


Unloading of bogie
Bogies assembling & set up
Lifting work platform
Work Platform on SPMT
Lashing
Start shifting of work platform
Reached quayside and waiting for liftof
Lunch
Liftof of work platform from SPMT
Prepare SPMT for TSS
Lifting TSS
TSS on SPMT
Lashing
Start shifting of TSS
Reached quayside and waiting for liftof
Liftof of TSS from SPMT
Activities end for the day

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

OPERATIONS REPORT OF BALNAVES PROJECT - MOBILIZAT


V1.0

Prepared By :

3. Major Problem Encountered


NA

4. OTHER INSIGHTS/RECOMMENDATIONS
NA

5. FURTHER ACTION(S) REQUIRED


NA

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

OPERATIONS REPORT OF BALNAVES PROJECT - MOBILIZAT


V1.0
Prepared By :
6. OVERVIEW
The overall shifting activities of the structures were executed safely and successfully

7. ANNEXES

Assembling of bogie

Work Platform on SPMT

Shifting work platform

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

OPERATIONS REPORT OF BALNAVES PROJECT - MOBILIZAT


V1.0

Prepared By :

Liftof work platform from S

TSS on SPMT

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

OPERATIONS REPORT OF BALNAVES PROJECT - MOBILIZAT


V1.0

Prepared By :
Shifting TSS

TSS reached quayside

Liftof from SPMT

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

OPERATIONS REPORT OF BALNAVES PROJECT - MOBILIZAT


V1.0

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

Prepared By :

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

euerle SPMT

11/5/2013 10:25
11/5/2013 13:25
180

11/5/2013 14:20
11/5/2013 16:00
100

has caused delays for the


during our operation.
on of delays.

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

10

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

uccessfully

embling of bogie

k Platform on SPMT

ting work platform

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

11

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

of work platform from SMPT

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

12

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

reached quayside

of from SPMT

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

13

277981273.xlsx

JECT - MOBILIZATION
Edmumd Ng

file:///var/www/apps/conversion/tmp/scratch_4/277981273.xlsx

14

unit
axlelines
units
psc
buckets

Description
Bogie
Power Pack
Mini PP
Ballast Pump
RORO Ramp
Wedges
Jacking Timber
Transport Beam
36m Loadout Beam
5m Spreader Beam
9m Spreader Beam

You might also like