1.1 Daily Progress Report - 15.07.15
1.1 Daily Progress Report - 15.07.15
Project : RAF A3 RO
1. Manpower
MH
3. Weather
Group leader
18
Time
Helper
30
180
Sunny or Fine
Cloudy
Foreman
Safety officer
Engineer
30
Project Manager
7:00
8:00
9:00
10:00
11:00
Rainy
4. Progress of Yesterday
10
General
Excavator Operator
Compressor Operator
41
262
Total
6:00
2. Equipment/Machine
Q'ty
Unit
Item
No
Air Compressor
no
5. Action for Today ( 13/07/2015 )
General
Excavation for Duct Bank - 80 Meter completed
Trial Pit - towards C200 Bay - 4 Nos Completed
Trial Pit Towards TX - 3 Nos completed
132kv Kahramaa cable exposed up to tiles