CONSTRUCTION PROCEDURE
WORK FLOW-CHART
The work sequence of the bored pile construction is depicted by the following flow-chart.
Preparation Works
Setting center point of bored pile
Assembling Guide frame

If necessary

Setting of the Temporary Casing

Drilling Works

KODEN Test

Inspection:
Depth of bored hole
- Property of Bentonite
Inspection:
Diameter of bored hole
Vertical of bored hole

1st Cleaning of the Bottom Hole


-

Installation of the Rebar Cage (including Sonic


and core tubes)

Inspection:
Property of Bentonite
- Depth of bored hole
-

2 Cleaning of Bottom Hole (if necessary)

Removal of the Temporary Casing


Backfill with suitable material
SONIC Test
Core test (if necessary)
Grouting SONIC and core tubes
Completion

Stage 1
1.Pre-boring for temporary casing installation

Inspection:
Rebar cages (at yard)
Sonic and core tubes
Depth of bored hole by
using rebar cages

nd

Casting Concrete

Inspection:
Center point Deviation
Vertical of casing
Level of casing top

Inspection:
Slump of concrete
Level of concrete rising
Center of Pile
Level of top concrete
- Depth of bored pile by
using tremie pipe

Stage 2
1. Temporary casing installation by vibrator hammer.
Stage 3
1.Pumping of bentonite slurry for maintaining bored hole
2.Drilling of bored hole from EGL to Design Toe Level
Stage 4
1.Desanding the complete bored hole
2.Bentonite in bored hole will be pumped back to bentonite plant for treatment.
Stage 5
1.Lowering of reinforcement to the bored hole.
2. Hanging the rebar cage at the designed level.
Stage 6
1.Concreting of bored pile.
2.Pumping of displaced bentonite back to bentonite plant.
3.Overcasted concrete 500mm above design COL.
Stage 7
1. Extracting temporary casing after the completion of concreting 15 to 20 minutes.
2. Backfilling the bored hole with suitable backfilling material 1 to 2 hours after
the completion of concreting