Section C7: Program: 1. Schedule
Section C7: Program: 1. Schedule
SAKURA FERROALLOYS
PROJECT:
DOCUMENT:
ENQUIRY NO.:
1.
SCHEDULE
The following are the latest scheduled dates on the Project. The Supplier must accept the
scheduled completion dates or state in this Contract, other dates for the performance of the
work. Earlier dates are preferred.
No dates filled into the Suppliers guaranteed schedule columns will imply automatic
acceptance of the Proposed by Purchaser dates.
Day duration as indicated below, shall be expressed as calendar days and not working days.
See Attached Programme. Supplier to provide his acceptance of the program dates.
Activity
Suppliers Guaranteed
Schedule
Proposed Schedule
Start
Completion
Duration
Start
Completion
Enquiry
Adjudication
Order placement, Contract
finalisation
Effective date of Contract
Submission of Bond within
10 days from Contract start
(if applicable)
Submission of program and
required information
documents within 14 days
from effective date of
Contract/Purchase order
Submission of engineering
documents incl. joint review
(drawings, analyses, lists)
Proof of Malaysian DOSH
approval submitted to
Purchaser
Site Establishment
All equipment
manufacturing (Engineer to
specify)
Page 1 of 2
CLIENT:
SAKURA FERROALLOYS
PROJECT:
DOCUMENT:
ENQUIRY NO.:
Activity
Suppliers Guaranteed
Schedule
Proposed Schedule
Start
Completion
Duration
Start
Completion
Testing of electrical /
mechanical equipment at
Suppliers Works
Page 2 of 2