19) Which of the following statements is not valid in regard to global system landscape
a.
A global template can be used for the roll out of corporate CUST settings and
DEV efforts
b.
Management of different repository objects can be managed using name
spaces, and name ranges for the repository objects
c.
Merging and CUST settings delivered by the corporate office with local
CUST efforts can easily be done using change requests
d.
SAP provides different tools to aid the roll-out of a global template.
20) Which of the following statements is correct in regard to CUST and DEV changes?
a.
all changes are recorded to task in CUST change request
b.
the changes should be recorded to tasks in change requests for transport to
other clients and systems
c.
the changes must be manually performed in every R/3 system
d.
the changes can easily be made simultaneously in multiple clients.
21) Which of the following statements in regard to change requests is false?
a. The customizing organizer and the workbench organizer are tools used to view,
create and manager change request
b. A change request is a collection of tasks where developers and people performing
customizing record the changed they make.
c. All changes made as a result of IMG activities are recorded to customizing
change requests.
d. SAP recommends setting your R/3 system so that customizing changes made in
the customizing and development client are automatically recorded to change
requests.
22) For which of the following activities is the TMS (tcode STMS) not designed?
a.
b.
c.
d.
23) Which of the following statements is correct after you have successfully imported
change request into the quality assurance system?
a. The change requests must be released again to be exported to the production
system.
Compiled by Amarnath Jayaraman.
Caution: This is just a sample questionnaire, hence the appearance of these in the exam is
not guaranteed. For reference only.
b.
The change request has been successfully imported into the QAS
system
c.
The change request is added into the import queue of all other R/3
systems in the system landscape
d.
The project leader communicates the approval of the change request
a.
There can be only one TRANS dir in a system landscape
b.
All R/3 systems within Transport group share a common TRANS dir
c.
In a system landscape using heterogeneous platforms it is not
possible to have a common TRANS dir
d.
Only the PRD system can contain the TRANS dir
44) Which of the following statements is correct in regard to the settings governing
changes to repository objects
a. Only the customer name range should be modifiable in production systems.
b. Developments are possible in an R/3 system only if you have applied for a
development namespace from SAP
c. If the global change option is set to not modifiable, it nevertheless possible to
make changes in certain name spaces or clients that has their change option set to
modifiable.
d. The global change option should always be set to not modifiable for the quality
assurance system and the production system.
45) Which of the following statements is correct in regard to the R/3 systems belonging
to a transport domain?
A. They all share the same transport directory
Compiled by Amarnath Jayaraman.
Caution: This is just a sample questionnaire, hence the appearance of these in the exam is
not guaranteed. For reference only.
Which of the following cannot be used to restrict a client from certain activities?
The client role
The client-dependent change option
The client ID-number
A client restriction
The client-independent change option
54) Which of the following tasks can be performed using the client copy tools?
A. Merging application data from one client into another client
B. Copying only application data from one client to another client
C. Copying only Customizing data from one client to another client
D. All of the above
55) Which of the following tasks can be performed using the client copy profiles?
A. Scheduling a client copy to occur at a time when system use is low
B. Selecting the subset of application data that will be copied when a client copy is
executed
C. Providing required user authorization for the use of client tools
D. Determining the data that will be copied when a client copy is executed
56)
A.
B.
C.
D.
10
61) Which of the following requirements must be met before you can change both clientdependent and client-independent Customizing settings in a client?
A. The client settings must allow for changes to client-independent Customizing
objects
B. The client role must be Production
C. The system change option must be set to Modifiable
D. The client settings must allow for changes to client-dependent Customizing
62) Which of the following statements are correct when project leaders and project team
members receive only the recommended authorizations?
A. Only developers can create change requests
B. Only project leaders can create change requests, and are therefore responsible for
assigning project team members to change requests
C. Project team members can create and release change requests
D. Project leaders can release change requests
63) Which of the following statements are correct with regard to Project IMGs?
A. The Project IMG provides access to the Customizing activities defined for a
particular project
B. Customizing is performed in the project IMG tree structure
Compiled by Amarnath Jayaraman.
Caution: This is just a sample questionnaire, hence the appearance of these in the exam is
not guaranteed. For reference only.
11
12
13
14
15
16
Answers:
1. D
2. B
3. B
4. B
5
A, D
6 D
7. B, D
8. D
9 A
10. D
11. B
12. C
13. D
14. D
15. B
16. B
17. A
18. A, D
19. C
20. B
21 C
22. A
23 D
24 B
25 B
26 A, B, C
27 C
28 B
29 B
Compiled by Amarnath Jayaraman.
Caution: This is just a sample questionnaire, hence the appearance of these in the exam is
not guaranteed. For reference only.
17
A, B, C, D
B
C
A
D
C
B
C
D
A, B
B
B, D
A, B, C
A, B
D
B
B
C, D
B, D
B
A
B, D
D
C
C
D
B
D
E
A, D
B, C, D
A, C, D
B, D
D
A, B, C, D
D
A, B, D
D
B, D
A, B, D
C, D
C
A, C
B, D
A, C
B, C
18
D
D
D, E
B, C
A, D
B, C, D
A, C, D
A, B, C
B, C, D
A, B, C
B, C
A, D
A, D
A, B, D
B, C
19