Professional Documents
Culture Documents
Aquaponics Final Proposal
Aquaponics Final Proposal
Aquaponics Final Proposal
FARMS FINAL
PROPOSAL
3/19/15
EXECUTIVE SUMMARY
Our project is based around Solutions Farms, an aquaponics initiative, located in
Vista, California. The Farm Manager, Kevin Gorham, contacted Global TIES and the
ENG 100D: Design for Development course to help create an efficient, productive
and sustainable mechanism to transfer plants from a high-density raft to a low
density raft. Kevin Gorham works under a larger parent organization called Solutions
for Change, which emphasizes meaningful worker reintegration into the workforce
through a program called Solutions University. Thus, a more efficient means to move
plants from a high to low density raft would provide the workers the opportunity to
do work that was not menial and unproductive towards the large goal of Solutions
Farms. Our team, the Awkward Pontiffs, made two site visits and corresponded
through e-mail with Gorham to ideate and prototype our final design the
Triangular Rail System (TRS). This design incorporates the rectangular preference of
Gorham and also the qualities of a product he was looking for. The TRS maximizes
the rectangular bed space by using incremental angle increases of one-way rails,
which move plants along at 5 inches per day. The angle of each rail and the daily
movement account for the area of growth needed for plants to reach their full
maturation by the harvest period (6-8 weeks after germination). This design has only
achieved a design prototype phase, whereas a physical prototype has yet to be
made. We hope that our ideas, our descriptions and detail of our original TRS can be
of future use to Gorham and Solutions Farms.
Page 1i
12
Introduction
Problem Statement
45
Design Specifications
67
Technical Approach
89
Project Management
10 12
13 14
Recommended Solution
15 22
23
Economic Analysis
24
25 26
Sustainability Assessment
Ethical Issues
27
After Thoughts
28
Appendix A
29 32
Appendix B
33-34
Page 2
ii
Major - Nanoengineering
Contact way001@ucsd.edu
Project Roles Primary conctact with Kevin Gorham and Johnathan Tran,
materials research, cost analysis
Transferrable Experience: Barista at Peets Coffee and Tea at RIMAC
Annex, constant communication with managers and customers.
Major Nano-Engineering
Contact - ematios@ucsd.edu
Project Roles Solution Design, Engineering Analysis, Data Management
Transferrable Experience: Environmental Engineering and Environmental
System Research Experiences
Page 1
Page 2
INTRODUCTION
Our team, the Awkward Pontiffs, is working with Farm Manager Kevin Gorham of
Solutions Farms. Solutions Farms is an aquaponics initiative in Vista, California. An
aquaponics initiative is an innovative and self sustaining approach to traditional
farming. Aquaponics uses a soil-less medium to grow plants and fish culture to
supply nutrients to a tank of water, which the plants are floating in. The plants, in
turn, filter the water by removing the fish waste (nitrates and ammonia) and the water
is pumped back into the fish tank. Solutions Farms is a branch of a larger
organization called Solutions for Change. Solutions for Change is a community
centered organization which aims to solve family homelessness. Solutions for
Change has a program called Solutions University, which spans over 1,000 days and
takes in families, providing housing and adequate resources to the families to
reshape their lives. The program also provides health care, job training, childcare
and counseling. Solutions for Change has produced a 93% success rate of
participants not returning to homelessness and 77% of participants are able to find
full-time careers. Solutions Farms, by extension, has been integral to this successful
model for workforce reintegration. This is the background to our project, as Farm
Manager Gorham is looking for a way to maximize his workers time so that they may
work towards the goal of Solutions for Change. This context gives all the more reason
to produce an effective design that will not only help Solutions Farms become a more
successful aquaponics initiative, but to further empower the workers and help
transform their lives.
Page 3
PROBLEM STATEMENT
Solutions Farms, an aquaponics initiative that employs homeless families for
reintegration into the workforce, needs a labor and time saving mechanism to
facilitate plant growth so that workers will be able to focus on skill developing work.
OUR CLIENT
Our client Kevin Gorham, Farm Manager of Solutions Farms, needs a new method of
moving plants from high to low density growth, in which time and labor or
minimized. He has several showcase systems in his farm buildings, but the simple
styrofoam raft system is the most cost and output efficient and thus the implemented
system at the moment. Gorham is looking for a new method because he is expanding
his farm by three times. If he maintains the current raft schematic, the time spent on
moving plants from one raft to another is only compounded and thus will take more
time. To meet the goals of his parent organization, Solutions for Change, Gorham
wants to deviate from the menial labor of moving plants monotonously from one raft
to another, to work that provides more opportunity to learn and develop transferable
work skills. This is the larger goal for Gorham and Solutions Farms, and more is
outlined for the workers below. Gorham has the capacities of space for his farm and
also is open to ideas. What limits Gorham is primarily funds to expand in ways that
have been proven on the market and that are productive.
Page 4
care, housing and accountability development for the participants. Thus, if the
workers are able to utilize an efficient mechanism of plant transfer, then they
themselves will be able to focus on other tasks that will help them reintegrate into
the workforce after their completion of Solutions University. Ultimately, just as
Gorham wishes, the end users do not want to spend a full day of work moving plants.
This process may be productive for the farm, but is not a productive task for the
workers in regards to their skill and job development.
STAKEHOLDER ANALYSIS
High Power
Keep Satisfied
Manage Closely
Awkward Pontiffs
Kevin Gorham
Solutions Farms
Low Power
Monitor (Minimum
Keep Informed
Effort)
Low Interest
High Interest
Page 5
DESIGN SPECIFICATIONS
Solutions Farms provides a learning environment through a thriving aquaponics farm
for the homeless community in Vista, California. Currently, the farm has allocated
$170,000 of grant funds toward construction for an expansion that triples the current
farm size. Solutions Farms hopes to boost productivity via increased area and
operational efficiency during this transformation. Our team focus is to ameliorate the
laborious plant transportation process between high to low density rafts within the
$11,000 budget allocated for new rafts, with consideration to the $90,000 annual
budget and the restrictions provided.
ENVIRONMENTAL CONSTRAINTS
The expansion area of 196 by 640 inches is sloped, and thus Kevin prefers to
continue growing in rectangular beds that can keep level growth on the sloped
grounds of the farm. His current rafts are rectangular fit to float in 16.5 by 52.5 feet
beds, which allow him to produce 400 pounds of vegetables per week. The farm uses
2 inch round net pots, but it hopes to move to that of 1 inch to match industry
standards. At the end of the growing stage, lettuce for instance requires an 8 inch
diameter for maturity. Our design productivity of must meet current productivity, if
not increase it, to maximize profit.
ECONOMIC CONSTRAINTS
Solutions Farms currently sells all produce to Vista Unified School District. VUSD
gets to support a humanitarian cause while Solutions Farms maximizes profit - this
mutualistic relationship has created great demand for Solutions Farms crops, and
Kevin estimates VUSD will buy out crops up to four times the current harvest.
Page 6
SUSTAINABILITY CONSTRAINTS
The aquaponics farm, hence the name, uses only tilapia to nourish its USDA-certified
organic crops. To match the needs of increased plants, Solutions Farms has allocated
$80,000 to install 16 new fish tanks ranging from $1,600 to $3,600 apiece. For a longlasting and environmentally friendly investment, Solutions Farms currently utilizes
reusable, sustainable, and budget-friendly Styrofoam rafts which last approximately
3 years. The materials of our proposed design must be of similar cost and lifespan.
CONCLUSION
The constraints present give our team a unique situation to approach the problem
and also the opportunity work within these constraints to form a more viable solution.
Although these aspects prevent some market solutions to be used, we took it as an
opportunity to be innovative and develop unique alternatives.
Page 7
TECHNICAL APPROACH
In an ideal human centered design process, as shown in Figure 1, engineers
empathize with and consider input and feedback throughout the project. In
conventional engineering, on the other hand, engineers apply the same steps they
would to the design process as they would to a math problem, then also prototype
and improve the design until perfection. The takeaway of this lesson was, as CEO of
Design That Matters Timothy Prestero said in a TED talk, Theres no such thing as a
dumb user...just dumb products that were not designed with a human-centered
design process. Developing empathy and a search mentality is fundamental to
effective design.
FIGURE 1
The very first step should have been to empathize the project to understand its
importance and define the problem. We were introduced to the project via a
presentation by the ESW President as well as Aquaponics Project Leader Jonathan
Tran. Solutions Farms needs help developing a labor and time saving mechanism to
facilitate plant growth and worker contribution to tasks other than menial labor. The
Page 8
open-ended nature of their description turned our focused primarily onto the
problem, and we overlooked its altruistic mission to solve homelessness and
unemployment. Nonetheless, once all members of the team visited the farm,
interacting with Gorham and the environment allowed us to fully understand the
mission and problem; however, the visits did not occur until week 10.
Since the first meeting, design ideation progressed naturally for our creatively
talented team. With the open-ended project description they provided us, we mainly
brainstormed without heavy research. Throughout these first weeks, we solely based
our ideas on brainstorming during our team meetings, as well as feedback from
Tran. Our three designs were a combination of all the ideas brought up by the team:
the Magnetic, Lunchbox, and Expandable raft. As Week 8 and the Concept Selection
approached, we scheduled a second visit to the farm with the rest of our team
members, and updated Kevin Gorham on our progress.
Gorham lead us to different designs proven on the market. Though our ideations
were impressive, we lacked in market research of proven aquaponics systems.
Gorham expressed interest in the Japanese Granpa Dome, a rail system; meanwhile,
we discovered a vertical system through online research. Tran originally offered to
serve as our liaison with Gorham. However, we should have contacted Kevin directly
from the beginning for input and feedback because Tran similarly lacks in first hand
experience on the farm like members of Team Awkward Pontiffs.
After learning from our lack of communication, we increased contact with Gorham to
test our proposed solutions by user feedback. The following final design
recommendation is based on purely feedback, since our mechanism, a combination
of Gorhams existing system and the Granpa Dome, has never been designed
before.
Page 9
PROJECT MANAGEMENT
The main goal of project management is to maximize the efficiency of the project
group and deliver the best results within a period of time. Each project group is
handled differently according to the nature of the project, as well as the nature of the
group dynamic. Within a week of the assignment we identified the project statement
and the project scope. These helped us quickly assess the needs of the client and
develop a concrete plan for the execution of the project. The tasks were delegated
accordingly in terms of interest and schedule availability. The details of the
procedure will be explained below.
This project is considered a small, non-financial benefit group work that seeks to
improve the working structure of a humanitarian organization- Solutions Farms. We
are looking at a simple model that doesnt require marketing and financial
constraints on our part. With the help of project management tools, we were able to
identify the specific tasks as well as the time frame to complete them. We used the
Work Breakdown Structure to establish the 4 main tasks (Research, Design, Testing
and Presentation) and to determine the specific subtasks needed to carry out to
ensure the success of the project. Once the specific tasks were identified, we used
the Gantt Chart (see Figure 2) to set a time frame for each of these tasks, setting up a
timeline from the start to the end of the project time period.
The primary phase was the research phase. This included a wide range of analysis
from cost, materials, environment constraints to plant productivity. Since none of us
were familiar with the field of aquaponics we also allocated a great amount of time
understanding the different structures of aquaponic systems and exploring their
market.
Page 10
The design phase was concurrently run with the research phase. As we learned more
about the different options, we designed alterations to fit the environment constraint.
This process required frequent communication with the client, in order to make sure
that our newly improved designs aligned with the clients needs and expectations.
Our initial expectation of the design and testing phase, consisted on redesigning the
rafts and making a final prototype for the client. However as the research
progressed, as well as the clients growing interest in larger scale rail systems, the
project scope was reevaluated and the criteria for the design and testing phases
along with their timeline were readjusted. In the end, the project evolved into a
innovative, prolonged process of design. We consulted a top hydroponics farm in
Japan (the Grandpa Dome) and we successfully delivered a design that would help
the client achieve maximum efficiency with the incorporation of similar system.
Our testing phase involved a series of analysis and establishment of baselines to
help measure the impact of our design on the profitability of the farm. We have also
created animations to help visualize the concept of the design. We wanted to make
sure our client understands the potential impact of the product, as well as its
potential cost.
At last, the presentation phase ran concurrently with all of the phases above. The
main tasks of the presentation phase were given by the requirements of the class.
We delivered our thought progress, new findings and newly improved designs
through each Work In Progress presentations, along with our Concept Selection.
Through the constructive criticism and evaluation of each assignment, we took
concrete actions to improve upon our flaws and we hope to deliver a great final
presentation.
DIVISION OF RESPONSIBILITIES
Page 11
As mentioned before, the tasks were delegated according to the interest of each
team member and our schedule availability. We have a total of 6 members in the
Awkward Pontiffs group that have taken upon the task to deliver the best solution for
Solutions Farms aquaponics system. Our team lead, Vincent Pham, is in charge of
leading weekly team meetings, allocating members on more time pressing tasks,
making sure the project progress aligns with the initial objectives and bringing
creative, risk-taking ideas and improvements. Vincent is most familiar with the
clients background and the problem statement. Our client liaison, Wayne Yang, is in
charge of maintaining biweekly communication with the client as well as the cost
analysis and market research. Wayne helps deliver our new ideas and questions to
the client and makes sure that the client stays up to date with our design process.
Edward Matios and Brandon Whang are our design geniuses, they are in charge of
exploring new designs while coping with the clients opinion and environment
constraints. Brandon and Edward have been consistently delivered improved
designs over the past 8 weeks. Diana Wu Wong and Fumika Takazawa, our project
managers, are in charged of planning out the project, keeping up with the timeline,
ensuring the quality of the tasks delivered, and assisting other members on
miscellaneous tasks.
Page 12
DESIGN CONCEPTS
CONSIDERED
Labor
Algae Prevention
Unspecified
Concept Name
Constraint Met
Constraint Met
Constraints Met
Expandable Raft
Yes
No
Yes
Yes
Yes
Magnetic Raft
No
Lunchbox Raft
Vertical System
No
Yes
Yes
1. EXPANDABLE RAFT
This was the first and most intuitive solution. The raft would be modified to support
expansion along the x and y axis allowing the user to simply pull the edges of the raft
to lower the plant density allowing without the time consuming re-potting process.
However if you look carefully at the diagram, you will notice that the expandable raft
leaves a space in the middle and fails to cover the entirety of the waters surface and
therefore fails to meet our second constraint.
2. MAGNETIC RAFT
Page 13
This was our most creative solution. The magnetic rafts will use a magnetic grid built
into the water beds to dictate where the it would settle. It is a form of semiautomation that would simply require the user to un-anchor the rafts individual
parts. The rafts will flow into the low density bed using the grid to designate
placement, without human labor. Although this design would meet all the constraints
laid out above, it requires infrastructure, such as a connecting waterway between
high and low density beds, that is not currently in place and would be too difficult to
implement.
3. LUNCHBOX RAFT
This was our solution of choice. It would operate much like a lunch tray in that the
rafts would stack on top of each other. Each raft would have a lower individual
density, that when stacked on top of each other would form a larger raft of ideal high
density. This was a simple solution that would require little modification and allow for
swift transition to lower density beds, simply requiring the user to lift and move the
raft to a new bed (already at target low density). However this solution failed to meet
the constraint of light, as it leaves a vast majority of the water uncovered.
Furthermore, Kevin brought to our attention of a previously unknown constraint,
salmonella. Since the water is using fish feces as nutrients, having that water drip
onto the plants as you lift the top raft carried the risk of giving our product
salmonella.
4. VERTICAL SYSTEM
This system is not one we thought of, rather it was one Kevin suggested to us. The
basic principle of the vertical system was to utilize 3 dimensional space to get more
effective growing space and therefore higher production rates. If you had a 10 meter
by 10 meter plot of land, you could use that land to produce towers effectively
allowing you to plant on a 10 meter by 10 meter by 5 meter area/volume giving you
more plants for the same amount of surface area. Though it has been proven on the
Page 14
market, unfortunately it is both labor intensive and largely not preferable from
Kevins perspective so we did not continue on with this idea.
RECOMMENDED
SOLUTION
The Rail System design was chosen to be the recommended solution. The existing
rail system we looked to as an example, the Grandpa Dome, operates on circular
water beds to achieve maximum efficiency, since circular geometry provides a
smooth and gradual space gain for the plants as they move radially outward. Hence,
the major design challenge was to capture the essences of efficient circular-oriented
rail system design and implement them into a rectangular water bed.
PROTOTYPE 1.0
The initial rectangular-oriented rail system design efficiently moves plants from high
density region to low density region gradually by increasing the space between rails
1 inch per week. In order to produce fully grown plants by the harvest time, Solutions
Farms plants such as lettuce, require an initial 2 inch growing space and final 8 inch
growing space. The average growing time for Solutions Farms plants is 6 weeks (5
weeks for summer and 7 weeks for winter). Therefore, by having the pre-calculated
space-time gradient of 1 inch per week, the plants can gain extra growing space in a
systematic way throughout the growing process. Please refer to Figure 3 8 for this
explanation.
Page 15
Page 16
Page 17
As shown by the figures above, the colorful space covering rafts are used to better
visualize the weekly growing space gain, and each colorful bar strip represents
inch width. Plants are being spatially manipulated to gain 1 inch extra growing space
per week, starting at 2 inch growing diameter on week 1, 3 inch growing diameter on
week 2, and so on until finally reaching 8 inch growing diameter on week 6. The
design was shown to Kevin during our farm visit, and he provided high approval on
the design. According to Kevin, our prototype 1.0 can yield higher productivity than
the existing raft system. However, some improvements can still be implemented as
prototype 1.0 has the major constraint in 1-dimentional expansion. Subsequently, a
prototype 2.0 was generated to improve upon the constraint of 1-dimension
expansion. Per Kevins suggestion, prototype 1.0 schematic is included in this design
record as a valuable template for potential alternation and improvement.
PROTOTYPE 2.0
The final solution is an improvement upon prototype 1.0 to resolve its major
constraint in 1-D expansion: prototype 2.0 triangular rail design (refer to Figure 9). A
triangular rail system, a design that is capable of expanding plants growing space in
2-dimensional pathway gradually with the predesignated space-time gradient, was
created to resolve the issue of 1-dimensional expansion. The triangular rail system is
designed to operate manually to achieve space arrangement flexibility, reduce
mechanical maintenance, and most importantly to maintain labor force requirement
for Solutions Farms principle of assisting homeless individuals with job training
opportunities. However, it is ultimately up to Solutions Farms to decide whether or
not to implement this design in a fully automatic way or a manually operated fashion.
Prototype 2.0 operates much like prototype 1.0 in terms of providing plants with
extra growing space as time passed, also in the gradient of 1 inch growing space
gain per week.
Page 18
Page 19
Page 20
As shown by figure 10, the actual water bed width of 196 inches is scaled down to
match with the 2 inches space increment on the initial stage on the left side and 8
inches space increment on the right side. The angles are measured with respect to
the system boundary at the bottom. As one can observe in the Figure 10, the rail
tilting angle increases as the system progresses in order to gain a gradual space
gain from 2 inches to 8 inches. So is the rail length increases as moving up the
system with the increasing tilting angle. Theoretically, total number of railings is
calculated by 640 inches (water bed length) divided by 10 inches (2 inches initial
space + 8 inches final space), therefore 64 rails, on one side of the bed. Because the
triangular rail system operates in a complementary fashion where the other half of
the water bed would require the exact same dimensions to produce a supplementary
counterpart, as demonstrated by Figure 9, there will be a total of 128 railings in one
water bed (64 rails per system per bed times 2 systems per bed).Tilting angle 1 (1
from Figure 10) is calculated by taking the inverse tangent of opposite length of 6
inches (8 inches minus 2 inches) over adjacent length 196 inches (the width of water
bed) equaling 1.75 degree.
Subsequently, titling angle 2 (2 from Figure 10) is calculated by taking the inverse
tangent of opposite length of 12 inches (16 inches minus 4 inches) over adjacent
length 196 inches (the width of water bed) equaling 3.5 degree. Next, railing length
is calculated by the right triangle property: rail 2s length is derived by the square
root of 196 inches square plus 6 inches (8 inches minus 2 inches) equaling 196.09
inches; rail 3s length is derived by the square root of 196 inches square plus 12
inches (16 inches minus 4 inches) equaling 196.37 inches, so on. In order to calculate
the tilting angle and railing length of each rail efficiently, a computer programing
Page 21
language of applied trigonometry was used to calculate all the subsequent angles
and railing length, and the table data is displayed in Appendix A.
Please refer to Appendix A for the calculation table
The feasibility of implementation prototype 2.0 is now solidified. With the
projections for total number of 128 rails in one water bed (64 occupying half the
space), tilting angles for each rail, rail height with respect to bottom system
boundary, and the rail lengths, we calculated the theoretical plant production in both
weight and quantity. Each rail is capable of carrying a total of 24 plants (196 inches
rail horizontal projection length divided by 8 inches growing space) for prototype
2.0 in order to maintain a radial space separation from 2 inches to 8 inches.
Therefore, the total plant quantity production is 128 rails per bed multiplied by 4
beds (total beds in Solutions Farms) multiplied by 4 plants per rail harvested weekly
(plants harvested every 6 weeks lead to 1/6 multiplied by 24 plants per rail yielding
4 plants harvested weekly) which equates to around 2,000 plants or 3,000 pounds
(assuming average weight is 1.5 pounds per plant). It is important to note that these
are theoretical production estimate and it is often an overestimate. It is necessary to
conduct on-site experiment and data collection to confirm these plant production
estimations.
Page 22
TECHNICAL
IMPLEMENTATION
Our team has completed the research, design, and presentation phase. In the event
that one may choose the implement this solution, the next step is to test prototypes
on a small scale to reduce economic, functional, financial risks. Especially because
our design is original, the theoretical results may not match the actual. If applied to
this expansion phase of Solutions Farms, the ideal time limit for completion of
prototyping and testing will be prior to the end of construction.
First we begin with acquiring necessary materials of the raft. This includes primarily
PVC boards, nails, and motors if desired. To construct the rails, line them at the
specified angles carefully as shown in Appendix A: Prototype 2.0 Rail Angle and Rail
Length Calculation. The thoroughness with which the angle and position of rails are
implemented will be a large risk; one rail that misses its position will affect the next
rail and so on. This process should not be rushed nor given to untrained workers.
After construction, insert a small amount of germinated seeds, for experimentation
purposes, into the net pot and move them every 5 days across the rail. At the end of
the 4 to 6 week maturity period, harvest the plants by pushing them off to the end.
The triangular rail system that will maximize production and minimize labor is now
complete.
Page 23
ECONOMIC ANALYSIS
Working with Kevin's current growbed dimensions of 196 by 640 inches, the raw
materials cost of our PVC rail implementation for a single waterbed totals $1,817.11.
This pricing ultimately varies on what brand and dimensions of white PVC board is
used. We used a cost-conscious standard of a white PVC expanded sheet board with
dimensions of 0.236 by 48 by 96 inches from Interstate Plastics to calculate the
materials cost1. A total of 35 of these standard PVC boards will give us sufficient
material for a single growbed, and sums up to the price above with excess PVC to
use for additional growbeds (Interstate Plastics offers a 5% high-volume pricing
discount).
One of the future challenges includes the labor costs of cutting the PVC boards to fit
the rail design. With the rather large dimension of the grow bed, custom quotes for a
single PVC sheet of ~870 square feet were unfavorable due to mere size and
shipping difficulties. We had to scale down the dimensions for our standard order
size. This constraint will need to be addressed in the future should this design be
utilized for Solutions Farm's waterbed expansions.
The economic impact of using white PVC boards for our design, which substitutes
the use of Styrofoam rafts, costs Solutions Farms a significant investment. Solutions
Farms has an annual budget of $90,000 from government grants and private
donations, not including salaries and labor cost. Thus the cost of implementing PVC
as a new material fits well within the budget. The true benefit of our team
1
https://www.interstateplastics.com/Pvc-Expanded-White-Sheet-
PVCWX.php?sku=PVCWX&vid=201503180310-7p
&dim2=48&dim3=96&thickness=0.236&qty=35&recalculate.x=109&recalculate.y=12
Page 24
SOCIO-CULTURAL AND
ENVIRONMENTALLY
SUSTAINIBILITY
ASSESMENT
The extent of our project only goes as far as a design, as time constraints did not
provide us the opportunity to physically prototype. From our research of potential
materials that could be used, aside from the entire climate monitoring equipment
already owned by Gorham, we project that the most environmentally damaging
material will be the use of PVC pipes. PVC, or polyvinyl chloride, is a synthetic
Page 25
plastic polymer. It is well known and widely used due to its biological and chemical
durability, for example in sewage systems. Thus, though synthetic, PVC pipes are an
environmentally friendly material to be used on an aquaponics farms. Gorham has
also identified he uses PVC pipes in his grow beds already, giving us more reason to
choose this as a primary material.
Aquaponics farms themselves tend to be self-sustaining, and our Triangular Rail
System will follow in line with that ideology. Depending on the extent in which
Gorham wants to implement the idea we have proposed, it can range from a manual
method of progressing plants down the rails or using an automated system, which
would use electricity and thus fossil fuels to operate. This offset of a carbon footprint
would most likely be minimal compared to environmentally friendly greenhouses
and self-sustaining aquaponics system. That said, it is still an important aspect to
consider when implement this system.
We predict that the PVC pipe itself will be durable and not need frequent
maintenance or replacement, thus creating a one-time if not relatively low cost for
implementation of the rail system. If the Triangular Rail System can be produced
with high quality material and construction, we predict that the environmental
impact of producing the piping will be negligent due to the long lasting use of the
pipe.
Hence, short term impacts would come with implementation while long term impacts
would actually produce positive outcomes, as an aquaponics system is more
sustainable in general. In the context of Californias current water sustainability, it is
important to note that aquaponics farms are on average 97 percent more water
efficient than its traditional counterparts, meaning a drought stricken California
could invest more into innovative farming techniques.
Page 26
Ethical Issues
Solutions Farms is a non-profit organization that promotes the rehabilitation and
reintegration of people back into the workforce. However, being a relatively new
aquaponics farm, it falls short of its goals. According to Kevin the farms plants
produced per square feet is unable to keep up with the rising demand of his
expanding market. He also regrets the fact that a significant amount of time the
workers spend on his farm is invested in menial labor instead of work that could
possibly further benefit and prepare them for the workforce. Although the goal is to
increase efficiency and production, over productivity and hyper efficiency hold the
possibility of derailing solutions Farms from its original purpose.
It is vital to keep in mind that Solutions Farms is a for-profit organization that devotes
all proceeds towards the benefit of others. If we make a system that requires no
labor, the system loses its value in rehabilitating people. Furthermore, if in doing so
we make the system extensively more productive than the current one, the
administrators of the farm could be tempted to switch from to a profit-focused farm.
As far as mitigation strategies go, we should not implement any. Any system can be
abused by the people in power. We have faith in Solutions Farms and Solutions For
Change, and hope that they use whatever benefits we provide towards improving
their system and expanding their capacity, possibly allowing them to take in more
people into their rotation.
Page 27
Afterthoughts
As the project Awkward Pontiffs comes to an end, we look back at the growth and
progress of this project. We started as a group of individuals trying to solve a simple
raft problem to a team striving to deliver innovative designs centered around our
client's needs and preferences, a human-centered design. As we encountered our
many road bumps we learned to work together as a team and to face the problems
together. We grew more understanding and compassionate about the client and the
end user of this design. Although the design is still in its primitive stage, if our client
shows interest in the further development of it, we would be more than willing to
follow up with this project and eventually see it succeed.
We would like to first thank Brandon and Denali for their guidance. We have grown
and improved every week with their constructive criticisms and encouragements.
We would also like to thank our client Kevin along with ESW liaison Jonathan, for
giving us the opportunity to work in this project and at last, we would like to thank
each one of the members who made the Awkward Pontiffs, for the hard work and
great collaboration this quarter.
Page 28
Appendix A
Initial Height
Final Height
Rail Length
Rail #
(degree)
(inch)
(inch)
(inch)
1.753
196
3.504
16
196.092
5.247
24
196.367
6.981
32
196.825
8.702
10
40
197.464
10.408
12
48
198.283
12.095
14
56
199.279
13.761
16
64
200.449
15.403
18
72
201.792
10
17.021
20
80
203.303
11
18.61
22
88
204.978
12
20.171
24
96
206.814
13
21.701
26
104
208.806
14
23.199
28
112
210.95
15
24.664
30
120
213.242
Page 29
16
26.095
32
128
215.676
17
27.493
34
136
218.248
18
28.856
36
144
220.952
19
30.184
38
152
223.786
20
31.477
40
160
226.742
21
32.735
42
168
229.817
22
33.959
44
176
233.006
23
35.149
46
184
236.305
24
36.304
48
192
239.708
25
37.427
50
200
243.212
26
38.517
52
208
246.812
27
39.575
54
216
250.503
28
40.601
56
224
254.283
29
41.597
58
232
258.147
30
42.563
60
240
262.092
31
43.5
62
248
266.113
32
44.409
64
256
270.207
33
45.291
66
264
274.372
34
46.146
68
272
278.604
Page 30
35
46.975
70
280
282.899
36
47.779
72
288
287.256
37
48.559
74
296
291.671
38
49.316
76
304
296.142
39
50.05
78
312
300.666
40
50.763
80
320
305.241
41
51.454
82
328
309.864
42
52.125
84
336
314.535
43
52.776
86
344
319.249
44
53.409
88
352
324.006
45
54.023
90
360
328.804
46
54.62
92
368
333.641
47
55.199
94
376
338.514
48
55.763
96
384
343.424
49
56.31
98
392
348.368
50
56.842
100
400
353.344
51
57.36
102
408
358.352
52
57.863
104
416
363.39
53
58.352
106
424
368.456
Page 31
54
58.829
108
432
373.551
55
59.292
110
440
378.671
56
59.744
112
448
383.818
57
60.183
114
456
388.988
58
60.611
116
464
394.183
59
61.028
118
472
399.4
60
61.434
120
480
404.638
61
61.83
122
488
409.898
62
62.216
124
496
415.177
63
62.592
126
504
420.476
64
62.959
128
512
425.793
Table 1: Each angle is measured with respect to bottom system boundary (referred to Figure 10);
initial and final heights are referred to rail position with respect to bottom system boundary (referred
to Figure 10).
Page 32
Appendix B
(Considered design concept pictures)
Vertical System
Page 33
Page 34