Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Sub: - Request for purchase of steel

Ref:-i) civil & strl. work of 45mva, SAF, at CFP


ii) Contract no:-CFP/Proj/ 45 MVA/WP-04/2014 Dt.12.08.14
the above work is being executed by us by deploying project as per requirement.
Regarding old civil foundation out of 51 foundations, 48 foundations have been
completed .various works like ECR, Furnace area, granulation pit, retaining wall, and
chimney and bag house to be taken up priority. ECR is G-4 storage building and
which involve lot of time, manpower and money. This work is executed by M/S
VIJAY.R. Ghate. He has submitted a request letter for purchase of steel. As per the
past experience this work was delayed two times due to steel and about 18 days
wasted for purchase of steel. This building requires a norms time and any delay in
ECR shall pour us in further trouble and other work can be completed in time expect
ECR, to cop up the demand of time and full the need of site it is favorable to
purchase the steel for early & timely completion of ECR, the cost estimation for
purchase of steel is as under.

240 MT @ 50,000/- per MT

Submitted for approval please

C.L. Shrivastava
(D.G.M. HSCL)

Unit Head - Chandrapur

= 120 lakhs

You might also like