The document is a request for approval to purchase 240 metric tons of steel for Rs. 120 lakhs to complete construction of an ECR storage building that is part of a larger civil and structural work project. Previous delays of 18 days occurred due to issues procuring steel, so purchasing the steel upfront will help ensure timely completion of the ECR building, which requires a strict timeline and any delays could cause further problems. Approval is requested for the steel purchase to facilitate an early and on-time finish of this critical component.
The document is a request for approval to purchase 240 metric tons of steel for Rs. 120 lakhs to complete construction of an ECR storage building that is part of a larger civil and structural work project. Previous delays of 18 days occurred due to issues procuring steel, so purchasing the steel upfront will help ensure timely completion of the ECR building, which requires a strict timeline and any delays could cause further problems. Approval is requested for the steel purchase to facilitate an early and on-time finish of this critical component.
The document is a request for approval to purchase 240 metric tons of steel for Rs. 120 lakhs to complete construction of an ECR storage building that is part of a larger civil and structural work project. Previous delays of 18 days occurred due to issues procuring steel, so purchasing the steel upfront will help ensure timely completion of the ECR building, which requires a strict timeline and any delays could cause further problems. Approval is requested for the steel purchase to facilitate an early and on-time finish of this critical component.
ii) Contract no:-CFP/Proj/ 45 MVA/WP-04/2014 Dt.12.08.14 the above work is being executed by us by deploying project as per requirement. Regarding old civil foundation out of 51 foundations, 48 foundations have been completed .various works like ECR, Furnace area, granulation pit, retaining wall, and chimney and bag house to be taken up priority. ECR is G-4 storage building and which involve lot of time, manpower and money. This work is executed by M/S VIJAY.R. Ghate. He has submitted a request letter for purchase of steel. As per the past experience this work was delayed two times due to steel and about 18 days wasted for purchase of steel. This building requires a norms time and any delay in ECR shall pour us in further trouble and other work can be completed in time expect ECR, to cop up the demand of time and full the need of site it is favorable to purchase the steel for early & timely completion of ECR, the cost estimation for purchase of steel is as under.