Concrete
RSB
17.87 cu.m.
4,404.16 kg.
211.93 cu.m.
33,564.39 kg.
ROOF DECK:
Concrete
RSB
48.32 cu.m.
8,935.6 kg.
TOTAL WEIGHT
278.12 cu.m.
46,904.15 kg.
21,696.88 kg.
2,386.88 kg.
1,500 kg.
1,866.13 kg.
74,354.04 kg.
Rebar Accomplishment:
Remaining Actual accom.
Billing
Underevaluation
For Ratio:
RDG-17A; Vol
RSB
2.94 cu.m.
594.97 kg. ;
Rough estimate
(9.86%)
202.4kg/cu.m.
Concreting:
BEAMS & GIRDERS
SUSPENDED SLAB
SLAB OF GRADE
COLUMN
TIE BEAM
FOOTING
STAIRCASES
COUTER SHELVES
WATER & F. TANKS
278.12 cu.m.
332.22 cu.m. (2214.81 sq.m.)
174.65 cu.m. (1164.33 sq.m.)
78.24 cu.m.
8.22 cu.m.
8.00 cu.m.
17.33 cu.m.
2.00 cu.m.
26.0 cu.m.
924.78 cu.m.
Accomplishment for concreting
Remaining
924.78 cu.m. / 4485 cu.m. (20.62%)
Actual accom.
79.38%
Formworks:
Remaining = 5327.6 sq.m./22526.85 (23.65%)
Actual accom 76.35%