Q1

Maximise Profit = $600L + $700F


L = No. of lamps produced
F = No. of ceiling fans produced
Subject to constraints
2L + 3F <= 12 (working hrs.)
6L + 5F <= 30 (assembly lines)
L,F >= 0 and integer
Rank 1: produce at least 4 lamps (goal 1) and 3 ceiling fans (goal 2)
Rank 2: Limit overtime in the assembly department to 10 hours (goal 3) and in the wiring
department to 6 hours (goal 4)
Rank 3: Maximise Profit
Q2
Minimise Cost = $5*R + $7*O
R = Qty. in pounds (industrial quality rubber)
O = Qty. in pounds (Oil Used)
Subject to Constraints:
3R + 0.25R2 + 4O + 0.3O2 >= 125 (hardness constraint)
13R + R3 >= 80 (tensile strength constraint)
0.7R + O >= 17 (elasticity constraint)
R, O >= 0
Solve using non linear programming