PT PETROKIMIA GRESIK(PKG)
GRESIK, EAST JAVA

Wuhuan
Eng. Co.,

REVAMP OF PHOSPHORIC ACID


PLANT PROJECT

Project No.

Concealment Record

WBS No.

Ltd

12057

No: 12057-PC70-1312057

Unit name: SA - Unit


Subcontractor: PT Marga Bangun Persada
T-1303 Wall elv. -0.150 up to 4.000

Construction Drawing No.

Didik Ariyanto
12057-03000-ST40-02

A. Carry out the work of closing the Foundation T-1303 Wall elv. -0.150 up to 4.000
1. The steel bars have been installed in accordance to construction drawing in good condition
2. The steel bars : 8,D10, D13 & D19
3. The method is using wire rope
4. Before installation formwork, the steel bars have been ascertained in good condition and
clean through the check list together

Inspection result

Concealed project contents and schematics

Concealed
Project

Project manager

Owner
Professional Engineer:

Contractor
Professional Engineer:

Subcontractor
Quality Inspector
Technical Responsible Person