International Capital Inc. (IC) is a small investment bank that specializes in
securing funds for small-to-medium sized farms. IC is able to use a standardized
project format for each engagement. Only activity times and unusual
circumstances change the standard network. The network information and
activity times for the latest client are given below:
Activity
Description
Immediate
Predecessor
--
C,E,F
G,E
H,I
Activity
Optimistic
Most likely
Pessimistic
10
16
19
28
24
13
10
28
14
17
17
29
47
Time in workdays
Construct the project network and using both statistical analyses as well as
Monte Carlo Simulation determine:
(i) The expected completion time for this project
(ii) What is the probability of completing the project in 85 days or less?