Event Analysis Report: 4 X 210 MW Cstps Chandrapur
Event Analysis Report: 4 X 210 MW Cstps Chandrapur
EVENT
ANALYSIS
1. Event No. 10
UNIT NO. 1
REPORT
Date
12.07.2008
Oil Support
170 MW
A, B, C, D, F
NIL
3. Nature of Event: TA Set withdrawn due to primary super heater tube leakage.
4. Observations :
1) Turbine trip first, 2) Turbine Emergency trip,3) Master trip Relay 86GT,4) TLR operated.
5. Analysis- BTL at primary S/H due to ash erosion.
6. Works carried out by maintenance section
Primary S/H top bank coil no. 68 lifted, in tube no. 19 (main failure) due to flue gas erosion
fish mouth opening observed. Secondary damage in coil no. 67 critical .
Total HP joints-30
Total X-ray-30 done
Date
14.07.2008
Date
15.07.2008
a) Short term
b) Long term
rectification of maximum such coils will be done during next O/H,2) Moreover complete
replacement of primary S/H coils programmed in 2011.
9. Remarks
NIL