4 x 210 MW : CSTPS : CHANDRAPUR

EVENT

ANALYSIS

1. Event No. 4

REPORT

Time 14:58 hrs.

UNIT NO. 3
Date 27.06.08

2. Operating conditions at the time of Event :


Load

Coal Cycles in service

Oil Support

210 MW
A,B,C,D,E
Nil
3. Nature of Event :
TA set tripped on Turbine trip mechanically indication with abnormal sound at front
pedestal.
4. Observations :

Turbine trip mechanically

TLR operated
Boiler tripped
Master trip relay 86 GT operated
Low forward power relay operated.

5. Analysis
MOP gear coupling found damaged and replaced by same.

6. Works carried out by maintenance section


Front pedestal top inspection cover was opened and pedestal was inspected visually .Gear
coupling & speed governors was inspected found ok externally. CVSM trial was taken found ok.
During rolling again sound was observed hence turbine hand tripped. Pedestal was opened. Main oil
pump gear was found damaged. Same was replaced.
7. Works carried out for the restoration by operation :
Boiler lighted up

Time - 04:05 hrs

Date 28/06/08

T-A Set Synchronised

Time - 13:41 hrs

Date 28/06/08

8. Recommendations to avoid reoccurrence :


a) Short term Rechecking of MOP gear coupling will be carried out in next opportunity.
b) Long term
HP/MOP alignment checking / replacement ,if required will be done during O/H.
9. Remarks

Nil

General Manager-I