Activity Predecessor Duration (days) Cost / Day Total Cost

A
2
300
600
B
A
3
400
1200
C
B
3
400
1200
D
B
2
200
400
E
D
3
100
300

Field Report at end of day 7


Activity
A
B
C
D
E

Actual %
Complete
100
100
33
50
0

Incurred Cost

CPI= BCWP/ACWP
CV=BCWP-ACWP
SPI=BCWp/BCWS
SV=BCWP-BCWS

600
1400
500
200
0

Field Report
A
B
C
D
E
0

Activity
A
B
C
D
E
Total to Date

ACWP
600
1400
500
200
0
2700

7 8 9 10
Actual % Complete

BCWP

BCWS

CPI

CV

600
1200
400
200
0
2400

600
1200
800
400
0
3000

1
0.86
0.80
1

0.0
-200
-100
0
0
-300

0.89

SPI

SV
1
1
0.5
0.5

0.8

0
0
-400
-200
0
-600